Mallorca airport runway upgrade with machine control

The latest machine control technology has played an important role in an airport runway upgrade for Mallorca. The Spanish island has long been a major tourist destination and its airport has been struggling to cope with demand, handling around 26 million passengers in 2016. Palma de Mallorca Airport is the third largest airport in Spain and during the peak summer holiday period, the massive influx of tourists makes it one of the busiest airports in Europe.
April 13, 2017 Read time: 3 mins
Two Wirtgen milling machines operating together were controlled by one system from Leica Geosystems
The latest machine control technology has played an important role in an airport runway upgrade for Malloca.


The Spanish island has long been a major tourist destination and its airport has been struggling to cope with demand, handling around 26 million passengers in 2016. Palma de Mallorca Airport is the third largest airport in Spain and during the peak summer holiday period, the massive influx of tourists makes it one of the busiest airports in Europe.

In November 2016, upgrade work for the airport’s southern runway commenced. The work has been carried out by a consortium called UTE Regeneración Pista Sur, which comprises the contractors MAB Obras Públicas and CONELSAN.

The consortium partners were given a specific task to carry out, correcting the slope of the runway and exchanging the horizontal and vertical runway signals. Because of the specialised nature of the milling job, this portion of the work was subcontracted to Iber Samop, which employed a PaveSmart 3D system from 265 Leica Geosystems on its mobile machines to deliver the necessary finish.

The milling job was carried out by a 2395 Wirtgen 200i milling machine, equipped with a PaveSmart 3D solution. In addition, the firm also had a second Wirtgen W2000 with a conventional levelling system. The 3D-controlled height of the first lane was used to provide the height reference for side plate height control of the next lane. The result was a no-slope-error propagation across lanes, while the side plate sensing delivered accurate joint-matching for the asphalt paving phase of the project. This ensured better quality asphalt joints and the set-up proved to be a cost-efficient use of two milling machines, operating with a single machine control solution.

Working in two shifts 24 hours/day, Iber Samop was able to use its equipment package to mill the 3km-long x 60m-wide runway in just seven days. The Leica PaveSmart 3D was used to measure the machine position and adjust the milling depth and cross-slope automatically. The benefit of the 3D milling solution is that it eliminates human error, while also provide a safer work environment and provides an accurate and uniform surface for a new asphalt pavement. In this way it helps to minimise costs of the new asphalt mix and eliminates the copying effect and long waves.


According to Iber Samop, this high rate of productivity could not be achieved without the use of up to date machine control equipment to guide the milling machines and deliver better quality results.

To meet the CS-ADR-DSN regulation covering the runways would have been difficult using conventional methods and systems. Iber Samop pointed out that with a profile milling job, the layer thickness can vary continuously. This can range from 10mm to 50mm just a few seconds later, according to the design. However, the firm said that the required evenness can be achieved by using the latest machine control technology to deliver an automated work process. The manual work process would require a surveyor in front of the machine at all times who would be busy measuring and marking the target milling thickness on the ground. But by using a machine control solution for milling, the human error in the conventional process can be eliminated and also allow for a safer working environment.

The work was carried out during a period of low air traffic volumes for the airport, so as to minimise delays for passengers. And with the runway now upgraded, Mallorca’s airport should be able to handle the 10% increase in passengers anticipated.

For more information on companies in this article

Related Content

  • Runway rebuild with Caterpillar machines
    February 2, 2017
    Kilgore Contracting has used Caterpillar machines to repave a runway at the Provo Utah Municipal Airport.
  • Data handling for efficient machine control
    October 16, 2012
    The rapid increase in information availability is transforming the construction sector. Conventional methods used for sourcing geographic data based on maps and localised sampling meant that there was often a lack of accurate information relating to ground conditions at specific areas where work was planned, often resulting in unwelcome surprises for construction companies along with additional costs for projects.
  • Producing recycled materials at an airport for surface use
    October 1, 2018
    Recycling of materials has been carried out at Cologne/Bonn Airport in a move to boost efficiency Using the Wirtgen KMA 220 mobile cold recycling mixing plant allows road construction materials to be recycled or upgraded onsite and avoids the need for numerous transport trips. The system is also economical, as became clear from a job at Cologne/Bonn airport at the end of 2017. There the plant, located immediately next to the job site, produced around 11,000tonnes of materials for a hydraulically bound ba
  • Sri Lanka Airport runway upgrade
    December 7, 2017
    Sri Lanka’s main international airport now features a new runway surface that will help improve air transport efficiency at the facility The project was carried out successfully, despite a tough time schedule, boosting safety at the airport. This new runway will help increase capacity at the airport, allowing Sri Lanka to develop the tourist sector on which the country depends heavily for its economic growth. The work at the international airport for Sri Lanka’s capital Colombo was carried out with the