Skip to main content

Jakarta Airport taxiway upgrade

Equipment from German firm Bauer has been used to help upgrade facilities at Jakarta Airport in Indonesia. The Soekarno-Hatta International Airport is located in Cengkareng, Banten, a suburb of the Indonesia’s capital city, Jakarta, is one of the largest airports in Asia. Handling around 63 million passengers in 2017 and over 447,000 flight movements/year, the aircraft handling facilities were becoming too crowded. The answer was to construct a new connecting taxiway linking the existing runways at the eas
June 7, 2019 Read time: 2 mins
Three Bauer BG 14 rigs as well as one BG 22 and one BG 28 were used for the work
Equipment from German firm Bauer has been used to help upgrade facilities at Jakarta Airport in Indonesia. The Soekarno-Hatta International Airport is located in Cengkareng, Banten, a suburb of the Indonesia’s capital city, Jakarta, is one of the largest airports in Asia.


Handling around 63 million passengers in 2017 and over 447,000 flight movements/year, the aircraft handling facilities were becoming too crowded. The answer was to construct a new connecting taxiway linking the existing runways at the east side of the airport. Previously, there was only one connecting taxiway located at the west side of the airport which supported for all aircraft movement.

PT 8350 Bauer Pratama Indonesia, the local subsidiary of Bauer Spezialtiefbau, was commissioned by PT Hutama Karya as main contractor of PT Angkasa Pura II (Persero), Indonesian Airport Company and the biggest Indonesian airport operator. The job was to carry out the ground improvement work for the construction of the new connection taxiway.

The project title was the East Connection Taxiway Phase 1 and the work included two main tasks: extensive ground improvement for the connection between the north and south runways, and foundation work for taxiway bridges over the airport’s main access road. This project was a continuation of the previous Secondary Apron project that was completed in May 2017, located at the north side of the airport where Bauer also carried out 98,300m2 of ground improvement work as the initial part of the East Cross Taxiway.

Ground improvement work was needed to increase the capacity of in-situ soil prior to pavement work. The in-situ soil is dominantly soft to medium stiff silty clay but with the work, it was expected to reach a CBR value (mechanical strength) of 6% under the pavement layer. Meanwhile, the allowable settlement is a maximum of 100mm in 10 years after construction.

The ground improvement was executed with 5-16m-deep full displacement columns (FDC) over a total area of 199,000m2. And for the foundation of the taxiway bridges, a total of 1,072 bored piles with diameters of 1.2m were drilled to a depth of 37m.

Three BAUER BG 14 rigs, one BG 22, one BG 28 and their accessories were in operation. The project commenced in February 2018 and was completed over a period of eight months in October 2018.

For more information on companies in this article

Related Content

  • Asphalt resurfacing at Miami International Airport
    February 8, 2012
    Improvements worth US$30 million are being carried out at Miami International Airport. The work includes runway resurfacing with specialist contractors having been brought in to handle the project. This is a busy facility handling some 34 million passengers/year and the work is being carried out over a period of 454 days in all, starting in September 2009 and due to finish in December 2010. The focus of attention is the upgrade to the airport's second longest runway, 8R 26L as well as the adjoining M and N
  • Revamped international airport for Tunisia
    March 2, 2015
    Carthage International airport upgrade – Mike Woof writes. Improvement works are being carried out at one of Tunisia’s major airports in a move aimed at improving capacity. A key component of the work is the upgrading of the runways and taxiways at Tunis Carthage International Airport (TCIA), allowing the facility to handle larger aircraft as well as higher volumes of air traffic. The work is being carried out by ETEP, which is building the new infrastructure to the latest international standards for runway
  • Airport upgrade
    July 2, 2012
    Four Dynapac CA602D single drum soil compactors are helping redevelopment work at Muscat International Airport in Oman. The machines are compacting around 160,000m2 of rockfill as part of a project to increase the airport's passenger handling capacity from 5-12 million/year by 2011. To minimise runway or taxiway flooding risks, the grounds are being raised 3m by local contractor Galfar Engineering & Contracting SAOG and this requires 10-12 million m3 of desert sand and crushed rock. The 19tonne Dynapac roll
  • Cebu Bridge sides joined in Philippines
    October 8, 2021
    The two sides of the Cebu Bridge in the Philippines have been joined.