Skip to main content

GPS machine control boosts road surface quality

The use of GPS machine control on sub-base has improved final rideability on a major highway reconstruction project. Innovative construction techniques have helped to upgrade a 9.6km stretch of the 307km long I-96 highway in the US state of Michigan. The Michigan Department of Transportation (MDOT) project was initiated in the third quarter of 2009 and was completed in the fourth quarter of 2010. Interstate Highway Construction acted as general contractor on the project, which included widening the shoulder
February 14, 2012 Read time: 4 mins
Kalin construction used five machines on site equipped with trimble GPS equipment

The use of GPS machine control on sub-base has improved final rideability on a major highway reconstruction project

Innovative construction techniques have helped to upgrade a 9.6km stretch of the 307km long I-96 highway in the US state of Michigan.

The 2630 Michigan Department of Transportation (MDOT) project was initiated in the third quarter of 2009 and was completed in the fourth quarter of 2010.

Interstate Highway Construction acted as general contractor on the project, which included widening the shoulders, updating a rest area parking lot and its exit, and reconstructing six ramps, including the two connected with the rest area.

2631 Kalin Construction handled the earthmoving portion of the total US$25 million contract. The company took the old road down to its sandy sub-base and then established new courses up to the concrete paved surface, which were laid by Interstate Construction.

Kalin Construction removed 203mm of continuous-reinforced concrete, which had a 102mm asphalt overlay according to the firm's project manager on the job Mark Bruzek. The concrete was then crushed in a portable plant and re-used on the site. The reinforcing wire mesh and the asphalt that was planed off with the company's 2395 Wirtgen W2000 cold milling machine was trucked off-site to be recycled.

The plan called for widening the shoulder from 1.52m inside, 2.13m outside to 3.66m inside and 3.66m for the outside shoulder according to Bruzek. To undercut and widen the highway shoulders the firm used Cat D6N and D6K dozers equipped with 2122 Trimble GCS900 grade control technology. A total of 211m3 of soil was moved over the entire I-96 reconstruction.

According to Bruzek, Trimble technology has been instrumental in helping Kalin maintain the tight schedule, even with the wet weather conditions. This equipment cut the on-site surveyor's time in half and eliminated most of the staking and stringlines. The firm was also able to reduce the survey team from three to two.

Kalin Construction has been using GPS and construction total station technologies since 2005, working with its local Trimble construction technology provider, SITECH Michigan. Before Kalin moved onto the site in force, Bruzek took the paper site plan prepared by MDOT and built a digital 3D model using Trimble Terramodel office software. He said that the digital plan allowed for greater detail and quality control of work on site.

Topographic data for the plan was confirmed and progress was monitored through Trimble site positioning system portable rovers, SPS880 and SPS882 Smart GPS Antennas paired up with TSC2 Controllers to measure, compute volumes, and use the digital 3D model that Bruzek generated.

Kalin Construction had two graders and three dozers working on the site, all of them equipped with Trimble GCS900 Grade Control Systems. Using the Trimble systems allowed the operator to get to grade faster, even with the complex I-96 designs according to Bruzek. He said that the on-board Trimble CB430 Control Box was used to determine the position of each tip of the motor grader or dozer blade and compare it to the design elevation to compute cut or fill to grade. The cut/fill data was then used to drive the valves for automatic blade control or passed to in-cab lightbars to provide visual guidance to the operator when using the indicate-only systems.

"One of our biggest challenges was to make sure we achieved the mandated grade with the 305mm sand base," Bruzek said. The firm had to move 138,000m3 of sand, so to achieve the expected +/- 12mm it relied on our Trimble total stations to achieve the fine-grade accuracy.

Kalin used both its SPS730 and SPS930 Universal Total Stations with feature Trimble MultiTrack technology to lock-on and track passive prisms for monitoring or controlling measurements, and active prism targets for dynamic measurements required for grade control.

After the sand base, Kalin Construction placed a 15mm open-graded drainage course using 4G-grade gravel, created on site from the company's crushing plant recycling the old concrete. The company had used its Impact Roller Technology Impactor 2000 for breaking up the concrete into 457mm pieces, which were small enough to feed the crushing plant.

The completed work was so good that it helped boost the overall rideability of the upgraded road section. And Kalin fully intends to use the same technology on other projects in the future.

For more information on companies in this article

Related Content

  • Topcon: A revolution in construction technology’s coming
    July 7, 2021
    The construction equipment industry is at a turning point. Topcon’s senior leaders believe that we are about to see a huge surge in the adoption of new construction technologies. The time is ripe as a new, younger and more tech-savvy generation comes to the fore. Governments could save billions, and where does the smartphone fit in?
  • Innovative earthmovers coming to market
    October 12, 2017
    A wide range of innovative earthmover solutions is now coming to market - Mike Woof writes Generally with major construction equipment exhibitions timed for the second quarter of each year, this is when manufacturers will roll out their latest earthmoving solutions. However 2017 has turned out to be something of an anomaly, with the major firms continuing to unveil new models. Firms have introduced new wheeled loaders, excavators, and dozers, although arguably, some of the most interesting developments
  • Iowa expects longer lasting road surface
    June 9, 2015
    In the US state of Iowa, tough paving specifications are resulting in contractors delivering road surfaces that will last longer. The Iowa Department of Transportation (I-DOT) expects to see a highway road surface last 20 years and recently let the contract for a 25.7km road resurfacing project for Highway 92 between Winterset and Greenfield. The 40km link between the two towns sees an average 1,365 cars/day travel on the highway, which was last worked on in 1994 and its surface was due for replacement.
  • Efficient asset management delivers
    April 25, 2013
    Maximising the economic benefit of infrastructure assets can be achieved through delivering better quality maintenance. Increasing utilisation of infrastructure follows on from those assets being in better condition. Clearly by tracking infrastructure condition closely, huge gains can be made in addressing technical issues before they become more serious and more costly, as well as minimising disruption. In UK city Birmingham, high resolution aerial photography from Bluesky is helping the city council under