GPS machine control boosts road surface quality

The use of GPS machine control on sub-base has improved final rideability on a major highway reconstruction project. Innovative construction techniques have helped to upgrade a 9.6km stretch of the 307km long I-96 highway in the US state of Michigan. The Michigan Department of Transportation (MDOT) project was initiated in the third quarter of 2009 and was completed in the fourth quarter of 2010. Interstate Highway Construction acted as general contractor on the project, which included widening the shoulder
February 14, 2012 Read time: 4 mins
Kalin construction used five machines on site equipped with trimble GPS equipment

The use of GPS machine control on sub-base has improved final rideability on a major highway reconstruction project

Innovative construction techniques have helped to upgrade a 9.6km stretch of the 307km long I-96 highway in the US state of Michigan.

The 2630 Michigan Department of Transportation (MDOT) project was initiated in the third quarter of 2009 and was completed in the fourth quarter of 2010.

Interstate Highway Construction acted as general contractor on the project, which included widening the shoulders, updating a rest area parking lot and its exit, and reconstructing six ramps, including the two connected with the rest area.

2631 Kalin Construction handled the earthmoving portion of the total US$25 million contract. The company took the old road down to its sandy sub-base and then established new courses up to the concrete paved surface, which were laid by Interstate Construction.

Kalin Construction removed 203mm of continuous-reinforced concrete, which had a 102mm asphalt overlay according to the firm's project manager on the job Mark Bruzek. The concrete was then crushed in a portable plant and re-used on the site. The reinforcing wire mesh and the asphalt that was planed off with the company's 2395 Wirtgen W2000 cold milling machine was trucked off-site to be recycled.

The plan called for widening the shoulder from 1.52m inside, 2.13m outside to 3.66m inside and 3.66m for the outside shoulder according to Bruzek. To undercut and widen the highway shoulders the firm used Cat D6N and D6K dozers equipped with 2122 Trimble GCS900 grade control technology. A total of 211m3 of soil was moved over the entire I-96 reconstruction.

According to Bruzek, Trimble technology has been instrumental in helping Kalin maintain the tight schedule, even with the wet weather conditions. This equipment cut the on-site surveyor's time in half and eliminated most of the staking and stringlines. The firm was also able to reduce the survey team from three to two.

Kalin Construction has been using GPS and construction total station technologies since 2005, working with its local Trimble construction technology provider, SITECH Michigan. Before Kalin moved onto the site in force, Bruzek took the paper site plan prepared by MDOT and built a digital 3D model using Trimble Terramodel office software. He said that the digital plan allowed for greater detail and quality control of work on site.

Topographic data for the plan was confirmed and progress was monitored through Trimble site positioning system portable rovers, SPS880 and SPS882 Smart GPS Antennas paired up with TSC2 Controllers to measure, compute volumes, and use the digital 3D model that Bruzek generated.

Kalin Construction had two graders and three dozers working on the site, all of them equipped with Trimble GCS900 Grade Control Systems. Using the Trimble systems allowed the operator to get to grade faster, even with the complex I-96 designs according to Bruzek. He said that the on-board Trimble CB430 Control Box was used to determine the position of each tip of the motor grader or dozer blade and compare it to the design elevation to compute cut or fill to grade. The cut/fill data was then used to drive the valves for automatic blade control or passed to in-cab lightbars to provide visual guidance to the operator when using the indicate-only systems.

"One of our biggest challenges was to make sure we achieved the mandated grade with the 305mm sand base," Bruzek said. The firm had to move 138,000m3 of sand, so to achieve the expected +/- 12mm it relied on our Trimble total stations to achieve the fine-grade accuracy.

Kalin used both its SPS730 and SPS930 Universal Total Stations with feature Trimble MultiTrack technology to lock-on and track passive prisms for monitoring or controlling measurements, and active prism targets for dynamic measurements required for grade control.

After the sand base, Kalin Construction placed a 15mm open-graded drainage course using 4G-grade gravel, created on site from the company's crushing plant recycling the old concrete. The company had used its Impact Roller Technology Impactor 2000 for breaking up the concrete into 457mm pieces, which were small enough to feed the crushing plant.

The completed work was so good that it helped boost the overall rideability of the upgraded road section. And Kalin fully intends to use the same technology on other projects in the future.

For more information on companies in this article

Related Content

  • Trimble introduces grade control simulator for bulldozer operator training
    April 19, 2013
    Trimble used bauma 2013 to introduce a construction grade control simulator for the specific purpose of training bulldozer operators. The simulator enables Sitech Technology dealers to deliver training on the GCS900 grade control system in a safe and realistic environment, without removing a bulldozer from production duties to carry out operator training. Trimble’s grade control simulator features fully interactive joysticks, a motion platform, decelerator and CB460 control box, enabling bulldozer operators
  • Latest GIS and software tools improve operations
    February 24, 2012
    Innovative GIS and software solutions are coming to market from the three key market players - Mike Woof reports Competition is strong in the field for GIS and surveying systems as well as the associated software. The three major players in the sector, Leica Geosystems, Topcon and Trimble, all invest heavily in research and development and continue to roll out new solutions for construction customers that will boost the efficiency of surveying as well as overall project implementation.
  • Maputo Airport runway rebuild
    March 26, 2019
    Rebuilding work has been carried out on the runway and taxiways at Maputo International Airport in Mozambique. The work was carried out for Aeroportos de Moçambique, with the engineering handled by NACO and US$64 million of funding being suplied by Agence Française de Dévelopement.
  • Runway rebuild for Detroit airport
    January 25, 2017
    A US contractor has employed equipment from Guntert & Zimmerman to help carry out a runway rebuild at Detroit Metro Airport The busy airport handles around 30 million passengers/year and the project had to be carried out in a tight timeframe as a result, with the paving crew working 16 hours/day to meet the schedule. Ajax Construction has been using its G&Z S850 paver for the work, which was needed as the existing concrete surface on runway 4L/22R had suffered from an alkali silica reaction (ASR). The