Bridge design using flow modelling techniques

SBG has set numerous engineering precedents with its hugely innovative Jamarat Bridge project in Saudi Arabia
February 17, 2012 Read time: 4 mins
The new Jamarat Bridge has been designed and constructed by SBG and is a complex mega-structure

SBG has set numerous engineering precedents with its hugely innovative Jamarat Bridge project in Saudi Arabia

The 2800 Saudi Binladin Group's (SBG's) Jamarat Bridge & Surrounding Area project is a landmark one and has won not just one, but two prestigious awards from the 713 International Road Federation (IRF) in its highly influential 2009 GRAA Competition. The IRF gave SBG an award in the category for Construction Methodology, as well as in the category for Research.

The new structure has been designed, planned and built by SBG using cutting-edge technologies, many of which relate to highway construction. The project is run under a design-build process and managed by a dedicated executive committee. The client for the Project is the Kingdom of Saudi Arabia, and its representative the Ministry of Municipalities and Rural Affairs is supervising the work.

The religious pilgrimage to a number of sites in Saudi Arabia, of which this is one, forms an important part of the Islamic Faith. In the last month of every lunar (Hijrah) year millions of people travel to these sites as part of their religious beliefs. For over 1,400 years the stoning of the three Jamarat in Muna Valley near Makkah, has been one of the main rituals of Hajj (pilgrimage). The stoning of Jamarat by pilgrims is repeated daily, in part or in whole, over a short period of a few days. At the beginning, the Jamarat site was marked by three simple monuments on the ground, allowing the small number of pilgrims to perform the stoning. However, the number of pilgrims started to increase and mixed with vehicular traffic, resulted in congestion as well as safety issues. A single level bridge was erected in 1975 and this structure allowed access for two million pilgrims. This also was proving unequal to coping with the growing number of pilgrims and because of the religious importance of the site, the Saudi Arabian authorities instigated an intensive research programme into a better solution. All feasible designs were considered and the authorities then brought in SBG to deliver a new structure capable of handling both current and anticipated numbers.

A key step in the project has been the site-specific research based on data collected over more than four decades. This research included reviews of past studies on pedestrian flow and crowd dynamics as well as actual data collection and analysis.

The designers used flow modelling techniques to simulate the way people move through the site. Using sophisticated algorithms has allowed the design team to predict how people walk through the structure, a similar technology as used in determining how vehicle 'wave' effects occur on busy, multi-lane highways. Advanced design software has been used which has allowed SBG to examine a range of options and factors and select the optimum layout. Because of the depth of research used the project stood out, a major factor in it winning an IRF award for this category.

Work commenced in 2006, with a large fleet of hydraulic excavators fitted with hydraulic breakers and other tools being used to demolish the previous structure. Once this was broken up and hauled away, site clearance could be carried out and the area prepared for the new structure. All the construction work has to be scheduled in set phases, with personnel and equipment cleared away from the site prior to the pilgrimage. Construction work has had to be carried out within a strict time schedule and using an enormous workforce of up to 11,000, requiring SBG to manage the project very precisely indeed.

The Jamarat Bridge is massive, measuring 550m long, having a maximum width of 100m and with six levels in all, while the total area of the structure is 217,417 m². The design is complex and in effect each level comprises a series of interlinked bridges that offer a maximum clear span of 97m. Each floor is 12m high while to provide ingress and exit there are 19 ramps in all, which measure a total of nearly 7.7km and vary in width from 24-42m. In additions the structure features the Souk Al-Arab Tunnel, which is 1.85km long by 34m wide and the King Faisal Tunnel, which is 2.25km long by 16m wide. Also providing ingress and exit are 11 escalator buildings with a total of 308 escalators, as well as six service buildings and two helipads.

The sheer scale of the work required has been enormous, especially given the time-frame. Some 9,040,000m³ of rock has been cut while 180,000m² of shotcreting and rock anchoring has been carried out. There has also been 5,000m³ of rock injection and 825,000m³ of backfilling.

The structure is built from precast concrete sections made at a special yard set-up specifically for the project around 30 km from the construction site. In all there is 1,170,000m³ of cast-in-place concrete and 1,550,000m³ of precast concrete, not to mention 477,400tonnes of reinforcement steel and 20,000tonnes of post-tensioning. The 5,028 precast, post-tensioned concrete segments have been precision manufactured at the purpose-built yard along with the 4,214 precast, pre-stressed concrete beams, with some of the latter units measuring up to 38m long. In addition there are 590,000m² of concrete paving tiles while the structure has required 160,000m³ of asphalt and because of the desert location, the structure also features an extensive water supply network.

For more information on companies in this article

Related Content

  • Germany builds its first major PPI autobahn project
    July 7, 2015
    Rebuilding of one of the oldest motorways in Germany is testing out the possibilities for public-private project road construction reports Adrian Greeman A freshly renovated section of the A8 Autobahn in southern Germany will be watched with some interest this summer as traffic begins driving along its rebuilt carriageway and additional third lanes. That is not because of any special road features, other than a distinctive reddish colour to its concrete surface, but because it is a first fullscale public
  • Norwegians would build new bridge and tunnel links
    June 18, 2021
    Norway’s road transport network is changing radically as the country gears up for greater EV use as well as a gradual phasing out of its traditional ferry links
  • Austria's new tunnel meets safety regulations
    July 13, 2012
    New safety regulations and high traffic volumes require new tunnel construction all across Europe. Mike Woof reports Anew highway tunnel now being built in Austria will boost traffic volumes and safety standards on a key European route. The existing Pfänder Tunnel lies close to Austria's borders with Germany and Switzerland and carries a heavy traffic volume, so a new parallel tunnel is under construction to help spread this load, increasing capacity as well as safety. Stringent tunnel safety standards have
  • Agua Negra tunnel between Chile and Argentina
    May 15, 2014
    The current Paso de Agua Negra is the highest border crossing between Chile and Argentina. On the Argentine side, the Agua Negra Pass is located at 4,765m above sea level and 260km from the city of San Juan in the province of San Juan in the north-west of the country. On the Chilean side, the pass lies 229km from the city of La Serena in the Coquimbo region. The pass can be accessed from the Argentine side via National Highway No 150 from the province of La Rioja, which runs for a total of 390km. From the C