VIDEO: Sarens raises the pylon for New Wear Crossing in Sunderland

February 13, 2017
It was as weekend working in Sunderland city, northeast England, for global lifting specialist 8569 Sarens.

Over the two days, the Belgian company gently raised a 1,550tonne steel pylon that will form the backbone of the New Wear Crossing – no official name yet – across the River Wear.

General work on the two-span cable-stay bridge started on the bridge in May 2015. The structure will be supported by the single double pylon and will have four vehicle lanes, as well as dedicated cycle and pedestrian routes.

The New Wear Crossing is part of a strategic transport plan to link the Port of Sunderland and Sunderland city centre with the A19 main road. The bridge project is the key project report in the upcoming January/February issue of World Highways, available later this month.

The 336m steel and concrete bridge will be part of 2.8km of new road layout. Width of the bridge will be 25m and the longest span 240m.Completion is set for the spring 2018.

Victor Buyck Steel Construction, working with 1622 Farrans Construction, spent a year fabricating the pylon at its canal-side yard in Ghent, Belgium. Apart from the 1,550tonnes tonnes of steel, around 550tonnes of concrete went into making the pylon that, because of its size, had to be constructed in the open air.

Also because of its size, Sarens was called in to gingerly shift the completed pylon onto two canal barges for transport to the sea port. “The sheer size and weight of the pylon meant that it was never going to be an easy task,” said Jim Kilcar, bridge supervisor for contractor 3005 Atkins, which is overseeing the New Wear Crossing project for Sunderland City Council.

For more information on companies in this article

Related Content

  • Drainage for new Wear Crossing in UK
    January 21, 2016
    In the UK the Lanes Group is carrying out the contract to build specialist drainage for the New Wear Bridge in Sunderland. The Lanes Group will carry out this work for the joint venture partners building the new bridge link.
  • New Wear Crossing cables fully installed and tensioned to 50%
    September 21, 2017
    Structural engineering company VSL International has installed all 28 cable stays of England’s New Wear Crossing and stressed them to 50% of their design load. The next stage of stressing the cables will happen next month and be to 100% of design load. This will allow the construction team to adjust and tension them just enough to lift the bridge deck off the blue steel temporary supports that were constructed in the river to take the weight of the structure.
  • Launch soon for the Sunderland Bridge’s deck across the Wear
    March 24, 2017
    The team constructing the New Wear Crossing near the English city of Sunderland is preparing for the final launch of the 300m bridge deck. In recent weeks, the legs of the 100m-tall centrepiece have been secured to the foundations within the riverbed and most of the rigging used to raise it into place has been removed. While the bridge deck was being painted, the bottoms of both pylon legs were filled with 175tonnes of concrete, The next major process will be to slowly pull the bridge deck out acr
  • Europe closes in on the crossings
    September 27, 2017
    The Mersey Gateway bridge project off England’s west coast passed a milestone recently with the first joining of two of the deck sections. The key segments, as the sections are called, link the north approach viaduct to the north pylon deck span and are the first of four deck-joins scheduled for this summer. In total, there are five sections of bridge deck and approach roads that need to be joined.