Video captures nocturnal bridge demolition in Germany’s Ruhr area

November 17, 2014
It was a 24-hour job to demolish the bridge called On Leiterchen that crossed over the A43 in the industrial Ruhr area of the German state of North Rhine-Westphalia.

Traffic was stopped in both directions between junctions Recklinghausen-Hochlarmark and Recklinghause-Herten.

Before the serious work of nibbling away at the concrete structure could start, a 50cm layer of sand was spread across the entire motorway to protect the pavement from excavator machine tracks and falling concrete. The bridge eventually jack-knifed in on itself.

Equipment used included Cat 336D and E excavators, three Hitachi ZX350 and one ZX470 excavators and two Mercedes Benz Arocs dump trucks.

Related Content

  • Long reach equipment simplifies demolition
    April 13, 2012
    Demolition is a highly specialised business, as the machinery required to carry out the work on high-rise demolition contracts can be very site specific. Today's high reach demolition rig is no longer simply a tracked excavator with a long boom, indeed some machines cannot be used as excavators at all. Likewise a machine that is dedicated to carrying a 2.5 or 3tonne shear or hammer will need to be built to take the stresses and strains of demolition life. Many of the ultra long boom machines are designed
  • CRCP is first choice for Belgian highway
    November 28, 2012
    Dan Gilkes reports on a Belgian highway upgrade When the Ministry of Public Works in the Belgian State of Flanders decided to reconstruct and resurface 19km of the N49 Antwerp-Knokke Expressway, continuously reinforced concrete paving (CRCP) with an exposed aggregate surface was the natural material choice. Indeed exposed aggregate, with its high grip and low noise benefits, has been the first option for all motorway surfacing work in Belgium since the 1980s. However, the €15.65 million contract is not a li
  • Sarens completes Nantes area A11 bridge lift
    December 27, 2023
    In France, Sarens used four Kamag SPMTs – self-propelled modular transporters – to move a bridge deck 70m and place it over the A11 at the autoroute’s Portes de Gesvres interchange.
  • Peri cantilever for Terfener Bridge
    May 17, 2021
    The Terfener Innbrücke reconstruction in the Inntal valley started in 2018 and is currently one of largest bridge construction projects in western Austria. In addition to providing planning services and onsite support, Peri has used its VBC Balanced Cantilever Carriage for the first time in Central Europe.