Gilpin Demolition gets tough with A38 overpass in Devon, UK

December 19, 2014
There was no need for a day shift when Devon-based Gilpin Demolition took on a timely challenge - demolish an overpass bridge in 15 hours and reopen the A38 by the following morning.

The 40m long and 8m high single carriageway bridge, made of 1,400 tonnes of steel and concrete, was an overpass near Rattery. By 8PM the A38 below had been closed and the bridge carriageways were barricaded, ready for Gilpin’s first crew to arrive and lay down 400tonnes of stone road protection on the A38.

Hydraulic breakers then moved in for the real work to begin, as the video shows – there was no sleeping on this job.

As the sun rose over the A38 next morning, the last of the crew moved off site, after 960 man-hours of work that included six dumpers completing 80 trips. The job was 100% finished and the material was 100% recycled.

Related Content

  • Effective, efficient long reach excavators
    February 15, 2012
    Long reach excavators now dominate the demolition sector - Mike Woof reports
  • Europe closes in on the crossings
    September 27, 2017
    The Mersey Gateway bridge project off England’s west coast passed a milestone recently with the first joining of two of the deck sections. The key segments, as the sections are called, link the north approach viaduct to the north pylon deck span and are the first of four deck-joins scheduled for this summer. In total, there are five sections of bridge deck and approach roads that need to be joined.
  • Multiple milling machines removing surface
    April 24, 2019
    Milling subcontractor Pavement Recycling Systems removed thousands of tonnes of reclaimed asphalt pavement (RAP) from a runway at Oakland International Airport in California recently. The firm used a fleet of six Wirtgen W 210i cold milling machines to remove the asphalt in less than 60 hours from Runway 12-30, along the shore of San Francisco Bay. In total, 47,000tons of asphalt were milled within a 60-hour time frame, nonstop day and night, plus a single-shift second phase a week later. The firm start
  • Repairs to piers on Italian viaduct
    July 17, 2012
    Hydrodemolition played a vital role in the repairs and strengthening of the multi-span Rio Verde Viaduct, one of the tallest in Europe, that carries the busy dual two-lane A15/E33 Autostrada della Cisa over a steep-sided valley in the municipality of Pontremoli, north-west Italy. Conjet hydrodemolition equipment was used to remove damaged concrete from the faces of the viaduct's rectangular concrete piers, which rise up to 136m from the valley bottom to the steel deck. A new and thicker concrete skin was th