Gilpin Demolition gets tough with A38 overpass in Devon, UK

December 19, 2014
There was no need for a day shift when Devon-based Gilpin Demolition took on a timely challenge - demolish an overpass bridge in 15 hours and reopen the A38 by the following morning.

The 40m long and 8m high single carriageway bridge, made of 1,400 tonnes of steel and concrete, was an overpass near Rattery. By 8PM the A38 below had been closed and the bridge carriageways were barricaded, ready for Gilpin’s first crew to arrive and lay down 400tonnes of stone road protection on the A38.

Hydraulic breakers then moved in for the real work to begin, as the video shows – there was no sleeping on this job.

As the sun rose over the A38 next morning, the last of the crew moved off site, after 960 man-hours of work that included six dumpers completing 80 trips. The job was 100% finished and the material was 100% recycled.

Related Content

  • Turkey’s new Marmara Highway project
    June 8, 2017
    By the end of 2018, a shiny new strip of asphalt will skirt around Turkey’s largest city, Istanbul, providing a new transport connection.
  • Zipping up road lanes – with Barrier Systems
    September 10, 2018
    QMB has a Lindsay Road Zipper on duty near Montreal. World Highways deputy editor David Arminas climbed aboard As vice president of Canadian barrier specialist QMB, based in Laval, Quebec, Marc-Andre Seguin is sanguine about the future for moveable barriers. On the one hand, it looks good. The oft-stated advantage of moveable barriers is that the systems are cheaper to install than adding a lane or two to a highway or bridge. Directional changes to lanes can boost volume on a road without disrupting tra
  • Act FAST when it comes to bridge maintenance, argues Cliff Weston
    February 27, 2017
    Deck waterproofing remains critical to a bridge’s structural integrity for its design life, explains Cliff Weston, director of Stirling Lloyd To properly maintain deck waterproofing there must be a willingness to look at solutions based on whole-life costing rather than just short-term initial costs. There are lessons to be learned from examples of prematurely failed infrastructure due to a focus on initial short-term costs.
  • Preparing a raceway with milling machinery
    November 6, 2018
    Contractor Continental Milling has played an important role in refurbishing the famous Pikes Peak Highway route in the US state of Colorado Working as a subcontractor for the Kiewit Corporation on the mill and overlay project, the Continental Milling crew was responsible for milling patches up to 213.4m long on the winding, two-lane highway known for its switchback turns and scenic vistas. The work was needed to prepare the route for the annual Pikes Peak International Hill Climb. Pikes Peak Highway fea