Gilpin Demolition gets tough with A38 overpass in Devon, UK

December 19, 2014
There was no need for a day shift when Devon-based Gilpin Demolition took on a timely challenge - demolish an overpass bridge in 15 hours and reopen the A38 by the following morning.

The 40m long and 8m high single carriageway bridge, made of 1,400 tonnes of steel and concrete, was an overpass near Rattery. By 8PM the A38 below had been closed and the bridge carriageways were barricaded, ready for Gilpin’s first crew to arrive and lay down 400tonnes of stone road protection on the A38.

Hydraulic breakers then moved in for the real work to begin, as the video shows – there was no sleeping on this job.

As the sun rose over the A38 next morning, the last of the crew moved off site, after 960 man-hours of work that included six dumpers completing 80 trips. The job was 100% finished and the material was 100% recycled.

Related Content

  • Asphalt airport runway refurbishment
    February 17, 2012
    Swedish contractor Peab Asfalt generally works on major road and highway projects in the inland portion of the country. However the company has shown itself able to take on a considerable challenge, by repaving an airport runway.
  • Balfour Beatty demolishes Scottish M8 bridge to create junction
    July 11, 2013
    Balfour Beatty has demolished a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland. The demolition of Cowhill Bridge is a major milestone for Ecosse Regeneration in the construction of Junction 4a. Using ten excavators equipped with hydraulic breakers and munching attachments, the four span composite construction bridge was successfully removed during a recent 10-hour night time closure of the M8.
  • Emergent markets key for formwork sector growth
    May 21, 2014
    Central and south-east Europe are hotbeds for new highway infrastructure projects utilising cutting-edge formwork solutions, while a number of leading formwork manufacturers are also looking at emergent markets for growth. Guy Woodford reports Travelling between Hungary’s capital Budapest and Southern Dalmatia now takes less time thanks to the Pan-European Corridor Vc – European route 73. Numerous tunnels and bridges are erected along the 397km stretch of the European route 73 through Bosnia owing to the
  • Meeting the challenge of desert runway resurfacing
    February 8, 2012
    Ferocious daytime temperatures can provide a tough challenge to construction firms working in desert conditions in Egypt's south. Despite the high daytime temperatures however, Egyptian contractor Orascom has managed to complete an airport project on budget and ahead of schedule, while meeting the client's tight specifications.