Gilpin Demolition gets tough with A38 overpass in Devon, UK

December 19, 2014
There was no need for a day shift when Devon-based Gilpin Demolition took on a timely challenge - demolish an overpass bridge in 15 hours and reopen the A38 by the following morning.

The 40m long and 8m high single carriageway bridge, made of 1,400 tonnes of steel and concrete, was an overpass near Rattery. By 8PM the A38 below had been closed and the bridge carriageways were barricaded, ready for Gilpin’s first crew to arrive and lay down 400tonnes of stone road protection on the A38.

Hydraulic breakers then moved in for the real work to begin, as the video shows – there was no sleeping on this job.

As the sun rose over the A38 next morning, the last of the crew moved off site, after 960 man-hours of work that included six dumpers completing 80 trips. The job was 100% finished and the material was 100% recycled.

Related Content

  • More challenges for Stonehenge A303 scheme
    August 1, 2023
    National Highways’ Road Investment Strategy for England’s strategic roads has committed to upgrading many the remaining single carriageway sections of the A303.
  • Norway’s Beitstad Bridge opens
    June 22, 2020
    Norway has officially opened the Beitstad Bridge over the Beitstad Sund, between the towns of Steinkjer and Verran in Nord-Trøndelag County.
  • Fast-track demolition
    June 18, 2012
    Heavy hydraulic breakers and a six-tonne combi cutter from Atlas Copco is said to have played a key part in enabling Armac to complete the demolition of the former Catthorpe motorway interchange viaduct within the 36 hours prescribed by the Highways Agency. Bridge dismantling experts Armac deployed no fewer than 10 Atlas Copco hydraulic breakers – six HB 4200, two HB 5800 and two HB 7000 units – to dismantle the 5,500tonne, 85metre long structure. In addition, Armac also used an Atlas Copco CC 6000 hydrauli
  • New German autobahn bridge under constriuction
    May 1, 2015
    Crane manufacturer Manitowoc has supplied six Potain cranes to German contractor Max Bögl. These machines are being used for constructing a new bridge carrying the A3 autobahn, close to Limburg. Working at over 70m high, the cranes tower over the Lahn Valley. The cranes for this project were supplied by Max Bögl’s subsidiary, Max Bögl Transport & Geräte. The three topless Potain MDT 222 cranes were selected for the work as they feature tip heights of up to 76.2m and can operate with a working radius of