Gilpin Demolition gets tough with A38 overpass in Devon, UK

December 19, 2014
There was no need for a day shift when Devon-based Gilpin Demolition took on a timely challenge - demolish an overpass bridge in 15 hours and reopen the A38 by the following morning.

The 40m long and 8m high single carriageway bridge, made of 1,400 tonnes of steel and concrete, was an overpass near Rattery. By 8PM the A38 below had been closed and the bridge carriageways were barricaded, ready for Gilpin’s first crew to arrive and lay down 400tonnes of stone road protection on the A38.

Hydraulic breakers then moved in for the real work to begin, as the video shows – there was no sleeping on this job.

As the sun rose over the A38 next morning, the last of the crew moved off site, after 960 man-hours of work that included six dumpers completing 80 trips. The job was 100% finished and the material was 100% recycled.

Related Content

  • New demolition excavators
    April 29, 2025
    Extended reach excavators offers versatility for demolition works, with new models now available
  • Topcon machine control units take the heat off an Alaskan contractor
    December 4, 2015
    Juniper, spruce, cranberry, cottonwood and rose. Most people think of pine trees and berries amid beautiful country fields. But for one contractor based just below the Arctic Circle in the US state of Alaska, the names represent a successful job completed using machine control. Valley General Construction recently finished a US$350,000 contract for the upgrading of country roads in the local borough of Matanuska-Susitna. The colourful names belong to roads in a heavily wooded residential subdivision located
  • Flyover replacement
    February 22, 2012
    French contractor DSD Démolition was one of three firms that worked on the recent demolition of the A55 highway flyover in Marseilles, France. The 20-year-old flyover stood near the harbour and formed part of a main route through Marseille leading to Lyon and Avignon. However, it was an ugly structure and spoiled the city's landscape so as part of the wider regeneration taking part in Marseille's harbour, the 1.3km bridge had to be demolished within three months. DSD Démolition had two operators for each of
  • bargain hunting, live onsite auction day in Donington, UK
    November 14, 2016
    It’s live onsite auction day in Donington, UK and it’s noisy. It’s also raining in early morning but that doesn’t put off the gathering crowd Buyers are milling around parked machinery. They kick tyres and slam doors. Some are behind the wheel, gingerly nudging vehicles frontwards and backwards or raising and lowering booms. Their partners stand a few metres away scrutinising the machine’s movements.