Gilpin Demolition gets tough with A38 overpass in Devon, UK

December 19, 2014
There was no need for a day shift when Devon-based Gilpin Demolition took on a timely challenge - demolish an overpass bridge in 15 hours and reopen the A38 by the following morning.

The 40m long and 8m high single carriageway bridge, made of 1,400 tonnes of steel and concrete, was an overpass near Rattery. By 8PM the A38 below had been closed and the bridge carriageways were barricaded, ready for Gilpin’s first crew to arrive and lay down 400tonnes of stone road protection on the A38.

Hydraulic breakers then moved in for the real work to begin, as the video shows – there was no sleeping on this job.

As the sun rose over the A38 next morning, the last of the crew moved off site, after 960 man-hours of work that included six dumpers completing 80 trips. The job was 100% finished and the material was 100% recycled.

Related Content

  • VIDEO of specialist contractor’s successful bridge demolition in Canada
    May 12, 2015
    Specialist contractor Priestly Demolition recently carried out a successful project in Ontario, Canada. The firm used its specialist skills to remove The Fountain Road Overpass, crossing Highway 401. A fleet of excavators equipped with demolition tools, including breakers and cutting equipment, was brought into to carry out the work using an overnight closure of the highway. Other machines including wheeled loaders and backhoe loaders were used to remove the broken out materials and to carry out other general duties.
  • Challenging bridge demolition
    March 2, 2012
    DEMOLITION and blasting experts Philipp Halter of Berlin, Germany, faced a challenging job: in just 48 hours it had to demolish the southern section of the Spandau Dam Bridge crossing the A 100. The efficient interaction of Atlas Copco hydraulic breakers and hydraulic CombiCutters, mounted on seven Volvo excavators, is said to have played a crucial role after following a carefully planned schedule. During Friday night a bed of sand was placed under the bridge to allow the girders and reinforcements torn dow
  • VIDEO – demolition of UK’s M1 motorway overpass
    April 17, 2015
    Specialist contractor Armac recently demolished a bridge over the UK’s busy M1 motorway. The work was carried out within a tight timeframe as this important route could only be closed for a short period at night over a weekend when traffic would be at its lightest so as to minimise disruption.
  • Australian bridge slides into position
    July 18, 2012
    A heavy rail crossing as part of Australia's EastLink motorway demanded great ingenuity and careful planning Most of the 88 bridges on the EastLink tolled motorway in, Melbourne, Australia were kept as simple and straightforward as possible. Contractor Thiess John Holland (TJH) developed its own precast yard 150km from the city, which provided many of the prefabricated materials required for the structures. This offered speed and economy while logistics and sequencing were vital for their erection. But the