Bridge deck launched for the New Wear Crossing, Sunderland (Video)

March 30, 2017

The 300m bridge deck of Sunderland’s New Wear Crossing has been successfully launched across the river.

The 4,750tonne concrete and steel deck was resting on the south side of the River Wear from where it was inched across to touch the north side in a 20-hour operation. It had to slide through the twin arched towers of the bridge’s double pylon on its way to its final position to connect the city regions of Pallion to the south and Castletown to the north.

The temporary blue steel nose will soon be removed and the remaining 40m section of deck will be built in-situ on the north side this summer.

The project to build the New Wear Crossing started in May 2015 and completion is expected in the spring of 2018. The bridge is phase two of the Sunderland Strategic Transport Corridor, which is a five-phase plan to improve links between the A19 and Sunderland City Centre and the Port of Sunderland.

Scaffolding attached to the top of the pylon will enable cable stays to be fitted, which will be attached to the deck and gradually stressed to take the weight of the bridge later this year. After that, the blue steel temporary towers supporting the deck will be removed and then lighting, road markings and safety features will be added.
Simon Fryer, a technical director of Buro Happold Engineering, who led the team that designed the bridge, said it’s been three years of hard but exciting work.

UK-based 1622 Farrans Construction and Belgian bridge specialist Victor Buck Steel Construction formed a partnership to create the FVB Joint Venture, main contractor for the bridge. FVB JV’s design team is led by Buro Happold Engineering and Roughan & O'Donovan, as well as independent checker 6801 Ramboll.

Victor Buyck Steel spent a year fabricating the pylon at its canal-side yard in Ghent. Because of its size, 8569 Sarens, a global heavy lifting and engineering transport specialist, was called in to gingerly shift the completed pylon onto two canal barges for transport along the canal to the sea port. Sarens transferred the pylon onto one, larger 100m-long seagoing barge.

When the pylon arrived about 1.5km off the coast at Sunderland, it was met by harbour tugs which brought it into port. On a specific high tide, it was carefully towed about 4.5km upriver to the site of the cofferdam between Pallion and Castletown.

The New Wear Crossing is the first bridge to be built over the River Wear in Sunderland for more than 40 years. World Highways recently featured the work as a <%$Linker:

2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 29953 0 oLinkExternal key project report Visit Key Project Report page false /categories/road-highway-structures/features/sunderlands-new-wear-crossing-takes-shape/ false false%> in the magazine and on the website.

For more information on companies in this article

Related Content

  • ARTBA launching student video competition for 2015
    February 18, 2015
    The American Road & Transportation Builders Association (ARTBA) is running its annual student video competition. This is set up to challenge students of all ages to produce a two-to-four minute video about America’s transportation infrastructure. World Highways continues to support this competition and has also posted links to those videos from past winners and runners up on its websites in previous years. The ARTBA Student Video Competition is now in its fifth year. The aim of the competition is to raise a
  • Scotland’s new Queensferry Crossing over the Forth Estuary
    December 23, 2015
    The new Queensferry Crossing under construction in Scotland will be the third landmark bridge spanning the Forth Estuary - Mike Woof writes When the new Queensferry Crossing over the Forth Estuary opens at the end of 2016, it will be the third landmark bridge to be built spanning this short stretch of water. Lying alongside the existing road bridge and the historic rail bridge, this new structure will be as groundbreaking as the two earlier crossings were at the time of their construction.
  • REMU launches Combi E8 screening plant
    April 16, 2013
    Finnish company Remu has launched its new screening plant, the Remu Combi E8. A non-clogging screening plant for preparing topsoil and processing various waste materials, the re-engineered solutions have increased screening capacity by a wider 950mm screening table and a new 2.6m3 feeder unit.
  • New quenched and tempered steels from NLMK Clabecq
    January 6, 2017
    NLMK Clabecq is launching new quenched and tempered steel products in 2013, with wider ranges of thicknesses and grades. During 2013, the Belgian specialist in thin and large steel plates intends to introduce superior grades for Quard, its abrasion resistant steel and Quend, its high yield strength steel. These introductions will to the range of solutions for heavy machinery manufacturers. Marketing manager Bernard Robins said, “Tests we are conducting with manufacturers are very positive. Welding our steel