ULMA on the Guadiana Bridge

Heavy onsite winds and the simultaneous renovation of both pylons were challenges for ULMA when it supplied scaffolding for work on the Guadiana International Bridge
October 5, 2021 Read time: 2 mins
The 100m-high pylons of the Guadiana International Bridge were covered with ULMA’s BRIO Modular Scaffolding to facilitate the repair of suspension cables (image courtesy ULMA)

The cable-stayed structure crosses the Guadiana River to connect the Spanish town of Ayamonte and Portugal’s Vila Real de Santo António, both popular tourist destinations.

The 666m, 5-span heavily trafficked composite bridge was designed by the architects José Luis Cancio Martins and Teixeira Duarte and opened in 1991. The bridge – with a 334m central span - connects Portugal’s Via do Infante de Sagres A22 Motorway to Spain’s Autopista del Quinto Centenario A-49 Motorway and is part of the European Route E1.

Renovation work includes a major repair of suspension cables and large-scale structural and mechanical maintenance, as well as repaving of the road deck.

ULMA provisioned 460tonnes of formwork and scaffolding for the work.

The 100m-high pylons were covered with BRIO Modular Scaffolding and access stairways to creating many distinct access points to facilitate the repair of suspension cables. The scaffolding design had to accommodate the pylon geometry and the presence of the suspension cables, while providing safe working spaces. ULMA’s design was further complicated by the presence of strong winds onsite.

ULMA was required to provide an efficient and timely response to the project’s various demands, not least enough scaffolding to renovate pylons simultaneously.

Two protective gantries – one for each pylon – were installed in an extremely limited space so renovation could be undertaken without interrupting traffic flow. In order to adapt to the limited space available and withstand the load of the scaffolding structures, the gantries were made from heavy-duty T-500 Shoring Towers combined with intermediate metal beams and ENKOFORM.

See the Key project report on page 20 of this issue of World Highways for ULMA’s work on the Cebu–Cordova Link Expressway in the Philippines.

For more information on companies in this article

Related Content

  • PERI’s balancing act at the Harpe Bru Bridge in Norway
    May 24, 2016
    Plans for the European Route E6 expansion in Norway include the 320m-long Harpe Bru Bridge over the Gudbrandsdalen Lågen River, at Sør-Fron in Oppland province. For the superstructure, PERI civil engineering technology experts developed a balanced cantilevered solution based on the VARIOKIT Engineering Construction Kit. Statens vegvesen, Norway’s agency for public road building, selected an extradosed cable-stayed bridge design – the first such bridge in Norway. It combines the load-bearing behaviour
  • PERI fills gap in Greek market
    February 19, 2013
    A team of Greek and German PERI engineers have developed a comprehensive formwork and scaffolding solution for the T4 bridge on the A7 motorway in Greece. The 160km long A7 connects Kalamata in the south to Corinth in the northwest of the Peloponnese peninsula. On one stretch of the motorway a 390m long arched bridge – known as T4 – is being used to close the gap between Paradisia and Tsakona. Set for completion in early 2014, two-thirds of the 22m wide bridge superstructure will be suspended on a steel arc
  • Towers of power: California’s Gerald Desmond Bridge Replacement
    May 8, 2019
    Challenging ground conditions meant a design rethink - and some engineering firsts - for California’s Gerald Desmond Bridge Replacement Project* The Port of Long Beach on Terminal Island south of Los Angeles is the second-busiest container port in the US. It handles around 15% of all imported goods, much of it with Asia. As the Port of Long Beach was growing in importance over the past half century, the 51-year-old Gerald Desmond Bridge has faithfully been delivering thousands of daily commuters to wo
  • Mabey Hire supports the Whorlton Bridge
    June 10, 2025

    Whorlton Bridge in England’s County Durham has had to be closed to traffic while a major programme of works is carried out. Every component is to be removed, refurbished and replaced.

    To facilitate the works, a bespoke catenary system has been installed, with Mabey Hire’s adaptable and modular propping equipment used to construct the temporary structure.