Sub-contractors used equipment from Tracto- Technik to renew two sections of an old grey cast iron water transport pipe covering a total of 200m as part of a complete street restructure in Linz, Austria. In order to prevent any traffic chaos and potential loss of trade for shopkeepers on busy Haidfield Street, while, at the same time, ensuring that the pipe cross-section ND 400 and the hydraulic pipe remained intact, Linz AG Water Department sub-contractors Swietelski- Faber (SF) decided to apply the static
October 31, 2012 Read time: 2 mins
Sub-contractors used equipment from Tracto- Technik to renew two sections of an old grey cast iron water transport pipe covering a total of 200m as part of a complete street restructure in Linz, Austria.

In order to prevent any traffic chaos and potential loss of trade for shopkeepers on busy Haidfield Street, while, at the same time, ensuring that the pipe cross-section ND 400 and the hydraulic pipe remained intact, Linz AG Water Department sub-contractors Swietelski- Faber (SF) decided to apply the static pipe bursting method to renew the pipes in three days over a recent weekend.

Using this method, pipes with the same size or larger pipes can be renewed in the same bore path. It is unusual to replace an old cast iron pipe with a new cast iron pipe of the same nominal size with the trenchless method, but it is possible and common with the pipe bursting method without any restrictions.

In order to burst the old cast iron pipe, to expand the bore channel and at the same time pull in the Duktus manufactured ductile iron pipe ND 400, obtaining a machine technology with tensile strengths was said to be crucial to SF’s chances of meeting its tight working deadline. A further requirement was the task of measuring and documenting the tensile strengths, as the pipes were only allowed to be strained up to 650 kN.

As a result, SF used 2738 Tracto-Technik’s (TT) GRUNDOBURST Type 1900 G with 1900 kN tensile strength pipe bursting system and the tensile strength measuring device GRUNDOLOG.

The measured and documented tensile forces were 500 kN, well below the permitted strains for the connection of the new pipe.

TT said the “exemplary co-operation” of all the companies involved in the project enabled the on-time completion of what was said to be one of the largest static pipe bursting method jobsite works ever undertaken in Austria.

For more information on companies in this article

Related Content

  • Developments in noise-reducing road surfaces
    February 17, 2012
    Mixtures with special additives are being produced for roads, offering noise reduction and aiding recycling. Patrick Smith reports. Noise-reducing road surfacings have been used in motorway construction for some time. But relatively new are noise-optimised surfacings used on roads in towns that do not follow a standard concept.Road trials with these materials have taken place in Germany since 2007 and have been prioritised due to the European Union Guidelines on the Assessment and Management of Environmenta
  • Turkey’s important new tunnel will improve transport links
    May 18, 2016
    Major advances in tunnelling will allow cars to travel underneath the Bosphorus sea channel in Turkey's Istanbul next year when its third road link is opened, writes Adrian Greeman. The Bosphorus is redolent with history and strategic significance. As one of the world's most significant sea connections, linking the landlocked Black Sea to the Marmara Sea and the Mediterranean beyond, it has been vitally important for trade and crucial for military access. It is also one of the biggest obstacles for land tra
  • Out of sight
    July 16, 2012
    With traffic volumes increasing around the world, many existing road links will need to be upgraded or replaced in coming years The need for new road tunnels is particularly intense in many dense urban areas, due to environmental requirements that mean new road links will have to be installed underground. However, improving existing road tunnel links is providing a very large part of the business for this specialised construction segment at present.
  • River level monitoring to reduce scour risk
    July 11, 2022
    An OTT ecoLog 1000 water level logger with cellular data connection to Hydromet Cloud was trialled upon the Vales Burn Bridge in Scotland