Sykes Pumps ballasting expertise adds weight to Forth float-outs

UK hire specialist, Sykes Pumps, is playing a vital role in delivering Scotland’s biggest transport infrastructure project in a generation - The Forth Replacement Crossing (FRC). Once completed later this year, the new road bridge will be the longest three-tower cable-stayed bridge in the world. Forth Crossing Bridge Constructors (FCBC) consortium is using 42,000 tonnes of steel. Getting all that steel out into the Firth of Forth is a delicate operation. The project involves transferring 7,000tonne se
June 17, 2016 Read time: 2 mins
Sykes Pumps at work on Forth Replacement Crossing
UK hire specialist, 8165 Sykes Pumps, is playing a vital role in delivering Scotland’s biggest transport infrastructure project in a generation - The Forth Replacement Crossing (FRC).

Once completed later this year, the new road bridge will be the longest three-tower cable-stayed bridge in the world. Forth Crossing Bridge Constructors (FCBC) consortium is using 42,000 tonnes of steel.

Getting all that steel out into the Firth of Forth is a delicate operation. The project involves transferring 7,000tonne sections of prefabricated steel and concrete deck onto float-out barges using SPMT (self-propelled modular transport) vehicles.

For that reason, Sykes Pumps is playing a vital role in managing the ballast of the float-out operation being delivered by heavy lifting and engineered transport specialist, Sarens.

Sykes Pumps has provided Sarens with 50 of its general purpose GP 150M diesel pump.

The GP 150M, with the Sykes Univac vacuum system, is used wherever there's a need for positive self-priming. The pump primes and re-primes automatically from dry and is powered by a 20kW Lister engine with many optional configurations.

Sykes Pumps worked with Sarens to calculate the ballast requirements for the load-on and load-off manoeuvres. It also invested in additional fittings and butterfly valves for the pumps to provide dual suction and discharge, reducing the number of pumps and personnel required on site and optimising efficiency for the ballasting operation.

“We are using two load out vessels for the project, each with 25 pumps,” says Alister Smith, project manager at Sarens. “We have worked with Sykes Pumps several times before and knew that the company could ensure that water pumped into and out of the vessels’ tank compartments is calculated accurately.”

Sykes Pumps’ float-outs expert, Richard Box, said he could advise the client on dual suction and discharge pumping, enhancing the efficiency of the ballasting operation and ensuring the float-outs are completed safely in line with the construction programme.”

For more information on companies in this article

Related Content

  • New version of world’s longest floating bridge
    August 12, 2014
    The creation of a new version of the world’s longest floating bridge in Seattle, in the US state of Washington, is among the world’s most eye-catching current bridge engineering projects. It is an impressive example of the health of the bridge replacement sector, particularly in the US, leaving it well placed for growth. Guy Woodford reports Already the world’s longest floating bridge at over 2,310m long, the Governor Albert D Rosellini-Evergreen Point Floating Bridge in Seattle in the United States is g
  • New Forth Road Bridge
    June 25, 2012
    Halcrow has been appointed by Transport Scotland to develop a bridge operating company contract to manage and maintain the new Forth Replacement Crossing and the existing Forth Road Bridge. The £1.6million commission, won in the face of stiff competition under Transport Scotland’s multiple framework agreement, runs to December 2014. “Halcrow’s proven expertise as a client advisor helped us to deliver a winning proposition that targeted our client’s needs,” said Donald Bell, Halcrow’s client manager. “Our ro
  • Formwork innovations help bridge building
    July 7, 2015
    A series of formwork developments are helping with challenging bridge construction projects around the world - Mike Woof writes In the Polish city of Krakow, a cost-effective cable stayed bridge is being constructed using a balanced cantilever technique. The current expansion of the Krakow metropolitan railway network (KST) requires the building of a crossing of the Krakow-Plaszow railway junction. Ensuring that daily rail operations remained unaffected during the construction of the 252m long crossing w
  • Harsco goes Forth
    June 25, 2012
    Harsco Infrastructure (HI) is providing bespoke scaffolding for a major refurbishment project being carried out on the famous Forth Road Bridge in Scotland. The £710,000 contract is seeing HI scaffolding used to allow work to be carried out to replace the large bearings which support each end of the structure, with no disruption to traffic using the bridge.