Sykes Pumps ballasting expertise adds weight to Forth float-outs

UK hire specialist, Sykes Pumps, is playing a vital role in delivering Scotland’s biggest transport infrastructure project in a generation - The Forth Replacement Crossing (FRC). Once completed later this year, the new road bridge will be the longest three-tower cable-stayed bridge in the world. Forth Crossing Bridge Constructors (FCBC) consortium is using 42,000 tonnes of steel. Getting all that steel out into the Firth of Forth is a delicate operation. The project involves transferring 7,000tonne se
June 17, 2016 Read time: 2 mins
Sykes Pumps at work on Forth Replacement Crossing
UK hire specialist, 8165 Sykes Pumps, is playing a vital role in delivering Scotland’s biggest transport infrastructure project in a generation - The Forth Replacement Crossing (FRC).

Once completed later this year, the new road bridge will be the longest three-tower cable-stayed bridge in the world. Forth Crossing Bridge Constructors (FCBC) consortium is using 42,000 tonnes of steel.

Getting all that steel out into the Firth of Forth is a delicate operation. The project involves transferring 7,000tonne sections of prefabricated steel and concrete deck onto float-out barges using SPMT (self-propelled modular transport) vehicles.

For that reason, Sykes Pumps is playing a vital role in managing the ballast of the float-out operation being delivered by heavy lifting and engineered transport specialist, Sarens.

Sykes Pumps has provided Sarens with 50 of its general purpose GP 150M diesel pump.

The GP 150M, with the Sykes Univac vacuum system, is used wherever there's a need for positive self-priming. The pump primes and re-primes automatically from dry and is powered by a 20kW Lister engine with many optional configurations.

Sykes Pumps worked with Sarens to calculate the ballast requirements for the load-on and load-off manoeuvres. It also invested in additional fittings and butterfly valves for the pumps to provide dual suction and discharge, reducing the number of pumps and personnel required on site and optimising efficiency for the ballasting operation.

“We are using two load out vessels for the project, each with 25 pumps,” says Alister Smith, project manager at Sarens. “We have worked with Sykes Pumps several times before and knew that the company could ensure that water pumped into and out of the vessels’ tank compartments is calculated accurately.”

Sykes Pumps’ float-outs expert, Richard Box, said he could advise the client on dual suction and discharge pumping, enhancing the efficiency of the ballasting operation and ensuring the float-outs are completed safely in line with the construction programme.”

For more information on companies in this article

Related Content

  • World’s largest bridge deck for KAIA expansion
    December 16, 2013
    A bespoke formwork solution from RMD Kwikform is playing a key role in creating the largest ever airport cast bridge deck as part of the multi-billion dollar expansion of King Abdulaziz International Airport near Jeddah, Saudi Arabia. The firm is also a leading player in the creation of arterial tunnels under the airport’s elevated roads, another key part of the project’s first phase works due for completion in 2014. Guy Woodford reports
  • Well structured maintenance
    January 4, 2013
    Major bridge maintenance and replacement projects across the world are extending the life of many impressive historic landmarks as Guy Woodford reports The Tamar Bridge, part of the main A38 trunk road linking Saltash in Cornwall with Plymouth in Devon, south west England, marked its 50th anniversary with a steel deck resurfacing project involving Stirling Lloyd's Eliminator bridge deck waterproofing system. Jointly owned by Plymouth City Council and Cornwall Council, the Tamar has a suspended length of 642
  • Underground routes for highways
    July 20, 2012
    Increasingly, and where possible, roads are being built in tunnels often for environmental reasons, writes Patrick Smith As part of the new M7 motorway development in the southwest of Ireland, the four-lane route crosses the River Shannon near Limerick, before it flows into the Atlantic. Centrepiece of the 10km long Limerick Southern Ring Road is the required tunnelling (675m long), which including the north and south entrance and exit ramps, means it will be 915m long. Completion of the work is planned for
  • Upgrade for Scottish road
    February 17, 2012
    Work is progressing on a £320 million (e385 million) project to upgrade a busy 18km stretch of the main A80 Glasgow-Stirling road in Scotland to motorway standard. The project, between the villages of Stepps and Haggs, is part of a massive infrastructure investment in Scotland's transport network, and construction work includes almost 8km of new dual-lane motorway and hard shoulders between