This runway builder perfected paving and landed remarkable results

This busy airport needed a complete runway renovation without disrupting daily scheduled take-offs and landings. Each workday, construction could start no sooner than 11pm and couldn’t end a minute past 6am. Without state-of-the-art technology from Trimble—including 3D machine guidance—and expert training from SITECH, this complex and high-precision project would've never got off the ground.
August 31, 2023 Read time: 2 mins

 

The Luxembourg Airport, located in Findel, is a major cargo destination in Europe. Along with ever growing passenger traffic, the airport’s one runway is 4 kilometres long and 60 metres wide—and was in need of complete renovation and repair after 30 years of operation in order for it to meet international standards.

Click here to watch the video

Airport operators needed a way to complete the runway reprofile without disrupting daily scheduled take-offs and landings. With an eye on speed, flexibility and quality, the operators opted to essentially build a new runway with different asphalt layers over the existing one. The idea was that milling machines would rectify the profile of the track while the asphalt pavers would apply the asphalt necessary to reach the desired level each night, reopening each morning for normal airport operations to resume.

“It was not possible to carry out this project without 3D machine control, with a classic workflow,” explains Christophe Latteur, with Karp-Kneip Construction. “We knew Trimble equipment and how it worked.” He continues, “Embracing 3D machine guidance—even in this particularly demanding context, everyone knows where he has to go, how he has to get there and what he has to do.”

A single Trimble MT900 Machine Target of the milling machine is supplemented by a Trimble GS420 Machine Control sensor. A manual control of the milled depth makes it possible to check the dimension and to validate the quantities of asphalt to be laid afterwards.

It’s a high-precision, highly complex mission with no room for delays—but it worked out. The operation was made possible thanks to a skilled team, 3D machine guidance, state-of-the-art technology from Trimble and the support and training provided by SITECH France, the local Trimble distributor. 

Click here to watch the video

Content produced in association with Trimble

For more information on companies in this article

Related Content

  • Great Eastern Bypass Interchanges Improve Safety, Connectivity, and Travel Times in Perth’s Eastern Metropolitan Regions
    June 27, 2023

    Located in eastern Perth, the Great Eastern Highway Bypass Interchanges project aims to upgrade two major interchanges at Roe Highway and Abernathy Road, which have become increasingly congested and caused significant delays for travelers. The AUD 380 million project will replace the current signalized intersections used by 60,000 motorists daily with two grade-separated interchanges.

  • Countdown is on: INTERMAT 2024 in Paris
    February 16, 2024
    Start today to build a better low-carbon tomorrow by registering to attend INTERMAT 2024, a global event for the building and civil engineering sector from April 24 to 27 at the Paris Nord Villepinte exhibition centre.
  • Make the Move to Data-centric Collaboration and Digital Delivery
    November 23, 2023

    Road infrastructure projects face unique challenges with complex terrain or design constraints, tight timescales, workforce shortages, and environmental considerations.

    Organisations who design, build, and operate our road and bridge infrastructure are looking at which latest digital technologies can help them overcome these challenges as well as improve their collaboration across the supply chain to reduce the risk of mistakes and delays.

  • New Bocimi Toll Road Aims to Reduce Travel Time and Boost Indonesia’s Economy
    April 20, 2023
    The Bogor-Ciawi-Sukabumi (Bocimi) toll road is a series of national strategic projects to help reduce traffic congestion along the existing factory-lined roadway, as well as enhance regional connectivity and tourism in West Java. Spanning 54 kilometers, the new highway corridor is expected to shorten travel time between the Bogor and Sukabumi provinces from two hours to 30 minutes and boost economic conditions in the surrounding Sukabumi area. Construction is divided into four phases, the first of which measures 15.35 kilometers and is already complete. PT Waskita Karya (Waskita) is the main contractor for the IDR 2.1 trillion second section, spanning 11.9 kilometers between Cigombong and Cibadak, and set for completion in 2023 after being delayed due to the pandemic.