Recycling highway material reduces waste and costs

The use of specialist equipment to produce hydraulically bound mixtures can save 30-40% on the cost of landfill and backfill it is claimed. The transportation and removal of old material from certain highway projects has long been a problem for contractors. But David MacLynn believes that the answer, in many instances, could lie in the use of hydraulically bound mixtures (HBM), which he says can save between 30-40% on the cost of landfill and backfill.
March 15, 2012 Read time: 4 mins
An ALLU SureMix being loaded with one of the company's buckets

The use of specialist equipment to produce hydraulically bound mixtures can save 30-40% on the cost of landfill and backfill it is claimed

The transportation and removal of old material from certain highway projects has long been a problem for contractors.

But David MacLynn believes that the answer, in many instances, could lie in the use of hydraulically bound mixtures (HBM), which he says can save between 30-40% on the cost of landfill and backfill.

David MacLynn, 2180 ALLU director, says the HBM system sees material from projects such as utilities trenches that are not fit for reinstatement materials in their unbound form, treated and reused with the addition of a binder.

“It has tremendous potential, particularly for utility contactors here, and there are substantial saving to be made as it eradicates landfill, transportation and other associated costs. HBMs are tried and tested.”

He points to other benefits, saying HBMs gain strength and stiffness and can be designed to suit a range of applications, including a reduced number of compaction passes and to eliminate settlement.

His company’s SureMix SM50, which is now being sold globally, took three years to develop and was designed and engineered by Welsh company Clayton Wheatway Solutions. It is earning its keep on major utility projects such as the East West Interconnector, County Flintshire, North Wales, which links Welsh and Irish electricity systems via a 260km long cable that comes ashore at Barkby Beach, Prestatyn. From here 30km of cable is being laid underground to a convertor station at Shotton.

Trench arisings removed from the excavation were sent to Welch Civils’ recycling centre close to the work location, and they were processed using the SureMix SM50 mixer and mixed with a proprietary binder to create a HBM suitable for trench reinstatement.
The HBM containing recycled trench arisings was used to reinstate the trench up to and including sub-base as part of a trial on a Type 2 road.

About 48,000tonnes of material was excavated from the highway and by utilising the material for HBM allowed the diversion of around 30,000tonnes of material from landfill.

Excavated material was transported to the recycling facility, and where possible, the vehicle returned to site loaded with reinstatement material to minimise empty truck movements, which are generally unavoidable when transporting material to landfill and collecting primary material from a different location.

The 63% reduction in truck movements to landfill yielded a cost saving of £20,000 (nearly US$32,000) and 47,000kg of CO2.

The HBM was mixed in a quality controlled manner utilising an innovative batching system. The self-contained mixing plant recorded the quantities of the components facilitating an audit trail and an efficient use of binder.

The 10tonne ALLU SureMix SM50 is a fully-automatic, purpose-built machine that uses a proprietary binder, and is readily transportable using a suitable hook lift truck.
Its weighing system delivers a very accurate product allowing laboratory designed mixes to be produced with a minimum of binder.

A generic Quality Protocol has been developed for the ALLU SureMix SM50 that is intended for customisation to suit individual operators of the machine and this defines what is required to allow production of HBM to the Series 800 specification.

Who's who...

East West Interconnector

Client: EirGrid

Local Authority: Flintshire County Council

Designer: ABB

Contractor: VolkerInfra Systems

Subcontractor: Welch Civils

HBM mixing plant manufacturer: Clayton Wheatway Solutions
MacLynn says that the SureMix SM50 pug-mill mixer provides a forced action mix compliant with Specification for Highway Works Series 800, and assures a thorough and even mix, essential when operating with low percentage weights of the binder. The binder storage hopper allows 1tonne bags to be loaded while working at ground level, and the ALLU SureMix SM50 can store sufficient binder for two hours operation (depending on the percentage dose).

“Rather than a contractor dumping the trench arisings, they could have it processed on their behalf at a price that would reflect significant savings in landfill and transport costs,” suggests MacLynn.

“Both the contractor and his client also benefit as they could then demonstrate they are using recycled material, not generating waste. They get a better quality product for less, and meet their environmental responsibilities and targets. It’s a win-win situation.”

For more information on companies in this article

Related Content

  • The new CBA asphalt granulator bucket
    October 1, 2021
    Available in two models: CBA 30 for 18 to 28-ton excavators, and CBA 40 for the 25 to 40-ton range
  • A new Marini asphalt plant for Strabag
    April 20, 2023
    Austria’s major contractor Strabag recently decided to purchase a new Marini Class Tower asphalt plant
  • Advances in tunneling machines coming to market
    November 19, 2015
    A diverse array of new tunnelling technologies will help boost productivity and cut project costs, while boosting quality - Mike Woof writes The worldwide market for tunnelling projects continues to be strong, with a series of major projects underway or planned for the future. These good market conditions have helped fuel research and development in new tunnelling equipment, designed to be more productive, more efficient and more reliable and able to deliver a higher quality of work. Drilling and blas
  • The use of concrete cutting tools and tips for users
    October 8, 2015
    Despite the proven importance of identifying metal targets and electrical lines before cutting into concrete, every day there are stories about mishaps that happen when the necessary reconnaissance is not done. In this article, a few firms that provide concrete scanning services weigh in on the critical importance of locating embedded and or buried obstructions by scanning for these features using ground penetrating radar (GPR). Also offered are tips for selecting the best GPR equipment and best practices f