Vital repairs to a drinking water transport pipeline in Norway included the first ever use in the country of trenchless water pipe bursting to fix damaged cast-iron pipes. Leaks caused by corrosion had become commonplace over 900m of the 40-year-old ND 600 cast iron-made pipeline in Trondheim. Due to the pipeline running 3m below a busy street and in front of a kindergarten and school, contracted civil engineering firm Sandum decided to replace the pipeline using a trenchless pipe bursting method rather tha
June 13, 2012 Read time: 3 mins
Vital repairs to a drinking water transport pipeline in Norway included the first ever use in the country of trenchless water pipe bursting to fix damaged cast-iron pipes.

Leaks caused by corrosion had become commonplace over 900m of the 40-year-old ND 600 cast iron-made pipeline in Trondheim. Due to the pipeline running 3m below a busy street and in front of a kindergarten and school, contracted civil engineering firm 5917 Sandum AS decided to replace the pipeline using a trenchless pipe bursting method rather than an open trenching method. The move also saved construction time and reduced costs by 30%.

During the four-month pipeline repair project, it was crucial to maintain its cross section. Corrosive soil conditions led to HD-PE pipe OD 710 x 52.2mm (with coating) being chosen as the new pipe.

As an active member of the Scandinavian Society for Trenchless Technology (SSTT) Trondheim residents and businesses are familiar with trenchless installations and replacement methods and were keen to promote the use of these techniques with the repair works.

Sandum said the diameter of the drinking water pipe was a particular challenge, requiring accurate planning in close cooperation with the engineering office 5918 Asplan Viak AS and machine manufacturer 2738 Tracto-Technik. Eco-friendly Bentonite was used to lubricate the pipe string, which significantly reduced the casing friction to make pipe pulling easier.

The pipe bursting started with a test section, with an option to continue the project. The Grundoburst 2500G with 250tonnes pulling force and a special roller blade for cutting the ductile cast iron pipe was deployed. An upsizing head of 830mm was used to displace the split old pipe into the surrounding soil.

After a successful test, the 900m of pipe requiring repairs was divided into seven sections, with the shortest being 120m and the longest being 170m long. The single 18m long segments of the PE pipe OD 710, PE 100, SDR 13.6 were welded together to form a complete pipe length for the respective section, pressure tested and securely connected using a pulling head.

The roller blade and expander head were attached to the bursting rods, which had been pushed through the old pipe in advance. When being pulled back the old pipe was cut and the new pipe pulled into the expanded void using Bentonite to reduce simultaneous casing friction. The tensile load affecting the new pipe was constantly monitored and logged with the Grundolog measuring device. An average tensile load of 500kN was measured, way below the legal limit.

For more information on companies in this article

Related Content

  • Zoomlion’s world record boom pump
    November 20, 2012
    Zoomlion has unveiled its innovative new truck-mounted concrete pump, which features a 101m boom. This innovative 101m unit is now a world record holder as the longest truck-mounted concrete boom pump. The machine was launched on the 20th anniversary of Zoomlion and is one of a new generation of products developed by Zoomlion and its Italian CIFA operation. The new machine has been developed from the existing 80m truck-mounted pumps, with its innovative lightweight composite boom being a key feature of the
  • Extraction operation benefits from haul road improvement
    May 23, 2014
    The trial of a novel compound at a site in Chile has shown how structural improvements can be achieved for dirt road applications Although the Barrick Gold Pascua Lama operation is a surface mining site, the experience with this technology is equally applicable for use on haul roads in large quarries or for dirt roads expected to carry heavy loads. This is of particular importance for transport in remote areas where large loads such as pre-cast bridge sections or girders for example may have to be carrie
  • Bridge engineering worldwide
    July 1, 2013
    Guy Woodford looks at vital bridge construction, repair and inspection projects in China, Europe, North America and Australia The Heron Road Bridge in Ottawa, Ontario in Canada is a vital link within the City’s transport network, as it crosses the Rideau River, which divides the east and west parts of the City. Constructed in 1966-1967, the Heron Road Bridge is approximately 275m long and includes six lanes.
  • Deep and wide with Wirtgen’s W 100 CFi compact milling machine
    May 14, 2018
    The spread of fibre-optic cables, especially for broadband internet access, is advancing rapidly across the world. The Upper Austrian district of Schärding, not far from the German border, is no exception. Engelhartszell is the second community to benefit from this technology. And the contractor, Hemmelmair Frästechnik from Linz, is also making use of cutting-edge technology - in this case made from steel and carbide. A Wirtgen W 100 CFi compact milling machine with deep milling unit is being used for tren