Record bursting water repairs

Vital repairs to a drinking water transport pipeline in Norway included the first ever use in the country of trenchless water pipe bursting to fix damaged cast-iron pipes. Leaks caused by corrosion had become commonplace over 900m of the 40-year-old ND 600 cast iron-made pipeline in Trondheim. Due to the pipeline running 3m below a busy street and in front of a kindergarten and school, contracted civil engineering firm Sandum decided to replace the pipeline using a trenchless pipe bursting method rather tha
June 13, 2012 Read time: 3 mins
Vital repairs to a drinking water transport pipeline in Norway included the first ever use in the country of trenchless water pipe bursting to fix damaged cast-iron pipes.

Leaks caused by corrosion had become commonplace over 900m of the 40-year-old ND 600 cast iron-made pipeline in Trondheim. Due to the pipeline running 3m below a busy street and in front of a kindergarten and school, contracted civil engineering firm 5917 Sandum AS decided to replace the pipeline using a trenchless pipe bursting method rather than an open trenching method. The move also saved construction time and reduced costs by 30%.

During the four-month pipeline repair project, it was crucial to maintain its cross section. Corrosive soil conditions led to HD-PE pipe OD 710 x 52.2mm (with coating) being chosen as the new pipe.

As an active member of the Scandinavian Society for Trenchless Technology (SSTT) Trondheim residents and businesses are familiar with trenchless installations and replacement methods and were keen to promote the use of these techniques with the repair works.

Sandum said the diameter of the drinking water pipe was a particular challenge, requiring accurate planning in close cooperation with the engineering office 5918 Asplan Viak AS and machine manufacturer 2738 Tracto-Technik. Eco-friendly Bentonite was used to lubricate the pipe string, which significantly reduced the casing friction to make pipe pulling easier.

The pipe bursting started with a test section, with an option to continue the project. The Grundoburst 2500G with 250tonnes pulling force and a special roller blade for cutting the ductile cast iron pipe was deployed. An upsizing head of 830mm was used to displace the split old pipe into the surrounding soil.

After a successful test, the 900m of pipe requiring repairs was divided into seven sections, with the shortest being 120m and the longest being 170m long. The single 18m long segments of the PE pipe OD 710, PE 100, SDR 13.6 were welded together to form a complete pipe length for the respective section, pressure tested and securely connected using a pulling head.

The roller blade and expander head were attached to the bursting rods, which had been pushed through the old pipe in advance. When being pulled back the old pipe was cut and the new pipe pulled into the expanded void using Bentonite to reduce simultaneous casing friction. The tensile load affecting the new pipe was constantly monitored and logged with the Grundolog measuring device. An average tensile load of 500kN was measured, way below the legal limit.

For more information on companies in this article

Related Content

  • Bitumen technology ideal for road repairs
    July 4, 2012
    Mike Woof discusses some novel developments relating to bitumen In the developed countries of Western Europe there is an increasing shift away from new highway construction to maintaining and rebuilding existing roads. In Germany alone, a network of asphalt roads extending more than 600,000km will have to be maintained or repaired. Highway maintenance techniques do vary between European countries but some commonalities exist. There are techniques that have been sidelined in the last few years but which now
  • Growing niche market for roller compacted concrete
    February 20, 2012
    A growing niche market for roller compacted concrete has prompted manufacturers to offer solutions. Mike Woof reports. Increased demand for roller compacted concrete (RCC) machines in certain applications mean that this is now a growing market, with manufacturers having developed new machines for this sector. RCC comprises uncrushed and/or crushed aggregate, hydraulic binders and may also contain concrete additives. It is mixed in a concrete mixing plant on or near the job site and one of its main benefits
  • Maximising cone crusher efficiency
    September 30, 2013
    Ensuring efficient cone crusher operation can deliver major economies of scale for quarrying facilities There are a number of ways in which cone crusher throughput can be optimised. One of the key issues is in keeping the system choke fed during operation, as this maximises the effectiveness of rock-on-rock crushing, extends the wear life of manganese components and ensures a quality product shape. A lack of feed causes inconstant loading, which affects the long-term life of internal components.
  • Roadside safety
    February 15, 2012
    A new safety barrier can protect pedestrians and property from out of control vehicles. Called Curb-I, the system is a triple bollard barrier assembly that can be quickly and easily installed on pedestrian walkways and in front of commercial areas to provide protection.