Record bursting water repairs

Vital repairs to a drinking water transport pipeline in Norway included the first ever use in the country of trenchless water pipe bursting to fix damaged cast-iron pipes. Leaks caused by corrosion had become commonplace over 900m of the 40-year-old ND 600 cast iron-made pipeline in Trondheim. Due to the pipeline running 3m below a busy street and in front of a kindergarten and school, contracted civil engineering firm Sandum decided to replace the pipeline using a trenchless pipe bursting method rather tha
June 13, 2012 Read time: 3 mins
Vital repairs to a drinking water transport pipeline in Norway included the first ever use in the country of trenchless water pipe bursting to fix damaged cast-iron pipes.

Leaks caused by corrosion had become commonplace over 900m of the 40-year-old ND 600 cast iron-made pipeline in Trondheim. Due to the pipeline running 3m below a busy street and in front of a kindergarten and school, contracted civil engineering firm 5917 Sandum AS decided to replace the pipeline using a trenchless pipe bursting method rather than an open trenching method. The move also saved construction time and reduced costs by 30%.

During the four-month pipeline repair project, it was crucial to maintain its cross section. Corrosive soil conditions led to HD-PE pipe OD 710 x 52.2mm (with coating) being chosen as the new pipe.

As an active member of the Scandinavian Society for Trenchless Technology (SSTT) Trondheim residents and businesses are familiar with trenchless installations and replacement methods and were keen to promote the use of these techniques with the repair works.

Sandum said the diameter of the drinking water pipe was a particular challenge, requiring accurate planning in close cooperation with the engineering office 5918 Asplan Viak AS and machine manufacturer 2738 Tracto-Technik. Eco-friendly Bentonite was used to lubricate the pipe string, which significantly reduced the casing friction to make pipe pulling easier.

The pipe bursting started with a test section, with an option to continue the project. The Grundoburst 2500G with 250tonnes pulling force and a special roller blade for cutting the ductile cast iron pipe was deployed. An upsizing head of 830mm was used to displace the split old pipe into the surrounding soil.

After a successful test, the 900m of pipe requiring repairs was divided into seven sections, with the shortest being 120m and the longest being 170m long. The single 18m long segments of the PE pipe OD 710, PE 100, SDR 13.6 were welded together to form a complete pipe length for the respective section, pressure tested and securely connected using a pulling head.

The roller blade and expander head were attached to the bursting rods, which had been pushed through the old pipe in advance. When being pulled back the old pipe was cut and the new pipe pulled into the expanded void using Bentonite to reduce simultaneous casing friction. The tensile load affecting the new pipe was constantly monitored and logged with the Grundolog measuring device. An average tensile load of 500kN was measured, way below the legal limit.

For more information on companies in this article

Related Content

  • Busy bridge in Beijing replaced quickly
    March 31, 2016
    The replacement of a very busy road bridge in China’s capital Beijing has been carried out successfully. Due to the volume of traffic using the bridge during week days, the work had to be carried out quickly so as to minimise traffic disruption. But despite being carried out in the centre of Beijing, the replacement work for the Sanyuan Bridge just took 43 hours from start to completion.
  • Soil compaction advances from key firms
    February 9, 2018
    The pace of development continues in the soil compaction sector, with key firms rolling out new machines - Mike Woof reports. New soil compaction technology is now being offered by several key manufacturers. Improved machines and new systems to boost performance are being offered by various firms. From BOMAG comes the availability of its Economizer system for its soil compactors. The technology has been well-proven in the BOMAG twin drum asphalt compactors as well as on the reversible plates and trench c
  • Emerson Industrial develops innovative leak-free drive system
    January 6, 2017
    From Emerson Industrial Automation come a novel worm gear reducer that is leak-free for 18 months. The patented Morse Raider Plus has a roll-burnished seal journal and double-lip seals, designed to keep contaminants out and lubrication in. A quill liner system is fitted to make disassembly less of a challenge. The product is said to be ideal for use in conveyors, mixers and bucket elevators. The computerised gear centering optimises the gear mesh for reduced heat and debris formation, eliminating backlash a
  • Emerson Industrial develops innovative leak-free drive system
    January 17, 2014
    From Emerson Industrial Automation come a novel worm gear reducer that is leak-free for 18 months. The patented Morse Raider Plus has a roll-burnished seal journal and double-lip seals, designed to keep contaminants out and lubrication in. A quill liner system is fitted to make disassembly less of a challenge. The product is said to be ideal for use in conveyors, mixers and bucket elevators. The computerised gear centering optimises the gear mesh for reduced heat and debris formation, eliminating backlash a