Record bursting water repairs

Vital repairs to a drinking water transport pipeline in Norway included the first ever use in the country of trenchless water pipe bursting to fix damaged cast-iron pipes. Leaks caused by corrosion had become commonplace over 900m of the 40-year-old ND 600 cast iron-made pipeline in Trondheim. Due to the pipeline running 3m below a busy street and in front of a kindergarten and school, contracted civil engineering firm Sandum decided to replace the pipeline using a trenchless pipe bursting method rather tha
June 13, 2012 Read time: 3 mins
Vital repairs to a drinking water transport pipeline in Norway included the first ever use in the country of trenchless water pipe bursting to fix damaged cast-iron pipes.

Leaks caused by corrosion had become commonplace over 900m of the 40-year-old ND 600 cast iron-made pipeline in Trondheim. Due to the pipeline running 3m below a busy street and in front of a kindergarten and school, contracted civil engineering firm 5917 Sandum AS decided to replace the pipeline using a trenchless pipe bursting method rather than an open trenching method. The move also saved construction time and reduced costs by 30%.

During the four-month pipeline repair project, it was crucial to maintain its cross section. Corrosive soil conditions led to HD-PE pipe OD 710 x 52.2mm (with coating) being chosen as the new pipe.

As an active member of the Scandinavian Society for Trenchless Technology (SSTT) Trondheim residents and businesses are familiar with trenchless installations and replacement methods and were keen to promote the use of these techniques with the repair works.

Sandum said the diameter of the drinking water pipe was a particular challenge, requiring accurate planning in close cooperation with the engineering office 5918 Asplan Viak AS and machine manufacturer 2738 Tracto-Technik. Eco-friendly Bentonite was used to lubricate the pipe string, which significantly reduced the casing friction to make pipe pulling easier.

The pipe bursting started with a test section, with an option to continue the project. The Grundoburst 2500G with 250tonnes pulling force and a special roller blade for cutting the ductile cast iron pipe was deployed. An upsizing head of 830mm was used to displace the split old pipe into the surrounding soil.

After a successful test, the 900m of pipe requiring repairs was divided into seven sections, with the shortest being 120m and the longest being 170m long. The single 18m long segments of the PE pipe OD 710, PE 100, SDR 13.6 were welded together to form a complete pipe length for the respective section, pressure tested and securely connected using a pulling head.

The roller blade and expander head were attached to the bursting rods, which had been pushed through the old pipe in advance. When being pulled back the old pipe was cut and the new pipe pulled into the expanded void using Bentonite to reduce simultaneous casing friction. The tensile load affecting the new pipe was constantly monitored and logged with the Grundolog measuring device. An average tensile load of 500kN was measured, way below the legal limit.

For more information on companies in this article

Related Content

  • Technology makes materials testing quicker and easier
    February 14, 2012
    Sophisticated technology is now being used to make the testing of a wide variety of materials quicker and easier as Patrick Smith reports. Ever since the CE mark became mandatory for asphalt mixes, it also became necessary and important to update the testing equipment and systems used for testing such materials.
  • Mexico’s new Jala-Puerto Vallarta Highway
    August 29, 2017
    Mexico’s highway infrastructure plays a key role in the country’s economy, carrying around 55% of its freight and 98% of its passenger traffic. To meet this demand, the network has 377,660km of roads in all. This is split between the 49,652km federal highway network, the 83,982km of state roads, 169.429km of rural roads and 74,596km of access roads. mHowever, although the federal road network manages to connect a large part of the country's strategic points, some stretches already present problems with satu
  • Mabey Hire supports the Whorlton Bridge
    June 10, 2025

    Whorlton Bridge in England’s County Durham has had to be closed to traffic while a major programme of works is carried out. Every component is to be removed, refurbished and replaced.

    To facilitate the works, a bespoke catenary system has been installed, with Mabey Hire’s adaptable and modular propping equipment used to construct the temporary structure.

  • Cold milling popular for road materials recycling
    March 2, 2012
    Milling techniques remain one of the most widely used recycling methods