Premium ponds

A series of balancing ponds are being used to create a sustainable drainage solution on the Highways Agency’s £375m 28km dual carriageway extension of the A46 in Nottinghamshire. Fearing that a doubling of the surface area of the Newark to Widmerpool trunk road would create excessive high surface water runoff, principal contractor Balfour Beatty and their consultant engineers, URS Scott Wilson, designed 12 balancing ponds, with the outfall from each controlled by Hydro International’s Hydro-Brake Flow Cont
April 25, 2012 Read time: 2 mins
A series of balancing ponds are being used to create a sustainable drainage solution on the 2309 Highways Agency’s £375m 28km dual carriageway extension of the A46 in Nottinghamshire.

Fearing that a doubling of the surface area of the Newark to Widmerpool trunk road would create excessive high surface water runoff, principal contractor 1146 Balfour Beatty and their consultant engineers, URS Scott Wilson, designed 12 balancing ponds, with the outfall from each controlled by 1402 HYDRO International’s Hydro-Brake Flow Control devices.

2759 Environment Agency guidelines require flow restrictions to be held at the predevelopment rate for greenfield runoff, to channel water volumes into local watercourses and control water quality. The A46 also lies adjacent to several environmentally, agriculturally and historically sensitive locations as well as within the flood plains of the Rivers Trent and Devon.

Designed with a permanently wet sump area, the balancing ponds also feature vegetated dry sections to ensure maximum entrapment of debris and silt at most stages of inflow. The outflow of each pond is fitted with a Hydro-Brake Flow Control or chamber, depending on maximum design flow required, from 27.5 to 66 litres/sec.

Work on the A46 upgrade scheme began in 2009, and is due to be completed in summer 2012. It is expected to improve traffic flow and
safety, while by-passing several villages.

For more information on companies in this article

Related Content

  • UK awards $5 billion traffic management framework contract
    May 4, 2012
    Arup, in partnership with URS Scott Wilson, has been appointed to a new UK national government procurement service framework for traffic management technology research and consultancy services. The pan-government collaborative agreement, which will be available to all UK public sector bodies from next week, is expected to delivery up to US$5 billion of contracts during it four-year lifetime.
  • Mini-bridge aids Forth repairs
    July 17, 2012
    An engineering "first" means that rehabilitation work on a vital Scottish bridge built over 40 years ago can be carried out smoothly A new report to the Forth Estuary Transport Authority (FETA) in Scotland recommends appointing Balfour Beatty Civil Engineering of Edinburgh as 'preferred bidder' to carry out the scheduled replacement of the bridge's main expansion joints in 2009. However, the report to the bridge authority says the tender price of £13.7 million (US$21.3 million) is some £5 million ($7.8 mill
  • Stonehenge Bypass contract awarded to consortium
    October 3, 2022
    The Stonehenge Bypass contract has been awarded to a consortium.
  • Extraction operation benefits from haul road improvement
    May 23, 2014
    The trial of a novel compound at a site in Chile has shown how structural improvements can be achieved for dirt road applications Although the Barrick Gold Pascua Lama operation is a surface mining site, the experience with this technology is equally applicable for use on haul roads in large quarries or for dirt roads expected to carry heavy loads. This is of particular importance for transport in remote areas where large loads such as pre-cast bridge sections or girders for example may have to be carrie