Paving an Iowa road

A slipformer from Power Pavers has been used to pave a road stretch in Iowa.
By MJ Woof February 4, 2025 Read time: 2 mins
Equipment from Power Pavers helped a contractor complete a paving job in Iowa ahead of schedule


Specialist firm Jones Contracting Corporation won the contract for paving nearly 4km of county road adjacent to the Lee County Fairgrounds in Iowa earlier this year. The firm knew meeting the schedule would be critical as the road would be a crucial link for the upcoming county fair. Some 15,000 people were expected.  

The project schedule established by Lee County was for the work to be completed in 35 working days. However, Jones Contracting completed it in just 25 ½ days.

The project, along the Business Route of County Road 218, ran from just north of the town of Donnellson to the county fairgrounds, then jumped to the south of the town. Overall, it included 3.8km of 102mm concrete overlay on top of the existing asphalt roadway, as well as 10 driveways and installation of new shoulders. The work was done in May, ahead of the heaviest heat of summer when the heated asphalt of the existing pavement might be problematic.

For the Lee County Overlay Project, both of the company’s Power Paver SF-1700 and SF-2700 slipform pavers were used. The company also has a TC-2700 texture/curing machine and a Power Curber 5700-D curb and gutter machine.

Upon completion of the job, Jones Contracting only had to grind the concrete at three headers, indicating that the concrete was smooth and required minimal reworking.

The company has been in business for ten years, and Patrick selected Power Pavers for his choice of machinery early on. “We’re extremely happy with Power Pavers. They are really great people to work with. They are located just up the road in Cedar Falls, so getting parts is easy,” said Patrick, adding, “And the machines they build are reliable and built to last.” 

 

 

For more information on companies in this article

Related Content

  • UK motorway bridge work
    June 10, 2025
    A new bridge now spans the UK’s busy M6 motorway.
  • Emergency areas for UK’s M1 complete
    April 16, 2025
    Emergency areas have been completed for the UK’s M1 motorway.
  • Tunisia is benefiting from key highway expansion
    November 28, 2012
    Work is underway in Tunisia on the westbound Highway from capital Tunis towards the Algerian border. This 60km link will run from the town of Oued Zarga to Boussalem and the work is being carried out by Italian contractor Todini and local company Soroubat. The bidding process for the 100km highway from Gabes to Medenine is now being opened, while bidding for the 92km road from Medenine to the Libyan border outpost of Ras Jedir opened in October 2012. Bids for the construction of the 61km of peripheral roads
  • Dual layer, hot to hot paving at German airport
    August 18, 2015
    An airport in Germany has seen the use of very innovative asphalt paving techniques, with the use of dual-layer, hot-to-hot working. The method was used to meet a very tight schedule for the runway rebuilding work, while also delivering the high quality required. Two InLine Pave trains from Vögele were used at Rostock-Laage Airport to lay a new surface and binder course. The operation was innovative as the process used both hot-to-hot, echelon paving as well as dual layer, hot-on-hot working. Using this