Motorway's tricky cable installation

The UK is now benefiting from the installation of sophisticated automated traffic management equipment and information signs on its motorway network. But with heavy traffic volumes on these roads, novel techniques have had to be implemented. One such operation, organised by client The Highways Agency and its consulting engineer A.One+, has recently been underway on the M56 motorway between Junctions 9 and 16 in north-west England under the Triple Package Advanced Works designation. To minimise traffic distu
February 6, 2012 Read time: 3 mins
The UK is now benefiting from the installation of sophisticated automated traffic management equipment and information signs on its motorway network.

But with heavy traffic volumes on these roads, novel techniques have had to be implemented. One such operation, organised by client The 2309 Highways Agency and its consulting engineer A.One+, has recently been underway on the M56 motorway between Junctions 9 and 16 in north-west England under the Triple Package Advanced Works designation.

To minimise traffic disturbance, it was decided to use horizontal directional drilling techniques for the majority of the crossing installations for the fibre optic cabling system. Ground investigations were carried out using bore holes at each crossing location and on both sides of the motorway, indicating that this was a suitable trenchless technique for the conditions.

The main contractor for the trenchless installation work was AE Yates, working with sister company AE Yates Trenchless Solutions. The majority of the crossings, 25 out of 26, were completed using various HDD drilling rigs and followed the project plan. The HDD bores varied in length between 40-100m and comprised the installation of four-way 110mm diameter conduits.

However, at one particular crossing location, the work site was restricted in space, both on the launch and reception sides, which meant that the use of the HDD technique was not possible, so another option had to be found.

Investigation of the options available led engineers at 2305 AE Yates to select the pilot auger microtunnelling technique for the limited-space site.

With the auger crossing site comprising compact sand and weathered sandstone, the correct choice of installation technique was vital, while still being able to operate in the confined spaces on either side of the motorway.

Careful consideration of the options available led to the choice of a 2302 Perforator PB85V pilot auger microtunnelling system. The auger crossing comprised the installation of a 45m long, 300mm diameter 'lost steel tube,' which was to act as a carrier pipe for four 110mm diameter conduit pipes supplied by Drain Centre of Wigan, into which the fibre optic cables for the traffic management system would be installed.

To complete the crossing the rig was located in the start shaft on the line and level required for the crossing. As the pilot bore progressed, the use of the laser-based optic electronic navigation system (OEN) allowed the pilot bore to be driven along the required route of the bore towards the target point.

Once the pilot bore was completed the cutting head was changed to an auger system to enlarge the pilot hole, removing spoil with the auger chain installed behind the auger cutting head. With the bore at the correct size the pipe installation was then completed by jacking the necessary pipe into place behind the auger chain while removing the displaced auger units at the reception shaft.

The HDD installations took an average of two restricted-hours night shifts each to complete, because of traffic management constraints, restricted working space and a requirement to dig the HDD rigs in at each site alongside live traffic on the M56 motorway.

Works on the auger crossing installation took five day shifts following shaft construction and site preparation. Using these guided boring systems allowed a tricky project to be completed on a site close to a motorway and in a limited space, a notable achievement.

For more information on companies in this article

Related Content

  • Mega city transport in Mexico
    June 13, 2012
    Rapid urban growth is resulting in massive mega cities with major transport needs and Mexico City is one of the world’s largest – Mike Woof reports Mexico City is a vast, sprawling metropolis and one of the world’s largest cities, resulting in huge problems for its inhabitants, particularly with regard to infrastructure. Measuring population size is an inexact science for large cities as suburban areas can add to the figures considerably, especially in developing nations where unplanned expansion is as comm
  • Surface quality a key trend in asphalt paving
    March 7, 2012
    Improved surface quality and improved machine design are key trends in the asphalt paving sector, Mike Woof reports There is a big difference in asphalt paving techniques in North America and Europe. In North America, the need to construct long stretches of highway quickly resulted in wide pavers offering high throughput capacity, with compaction equipment then being used to achieve the required density of the various courses. In Europe's highway construction projects, distances tend to be shorter and contr
  • Rock cutters added to American Augers line-up
    January 6, 2017
    American Augers and Trencor have come together under parent company The Charles Machine Works, to develop a four-model line of surface mining machines. Using an American Augers mining head, with a Trencor trencher chassis, the machines offer a cost-effective means of removing material without drilling and blasting. The machines offer cutting widths of 3.2-4.5m with maximum cutting depths of 0.91-1.1m.
  • Powerscreen machine aids in Australia’s key highway upgrade project
    April 16, 2018
    The major Pacific Highway upgrade in New South Wales is one of the largest road infrastructure projects undertaken in Australia. Connecting Sydney and Brisbane, the Pacific Highway is being upgraded to provide a four-lane divided road from Hexham to Queensland. The work commenced in 1996 and is scheduled for completion in 2020, with approximately 75%, a staggering 493km, of the work having already been completed.