Motorway's tricky cable installation

The UK is now benefiting from the installation of sophisticated automated traffic management equipment and information signs on its motorway network. But with heavy traffic volumes on these roads, novel techniques have had to be implemented. One such operation, organised by client The Highways Agency and its consulting engineer A.One+, has recently been underway on the M56 motorway between Junctions 9 and 16 in north-west England under the Triple Package Advanced Works designation. To minimise traffic distu
February 6, 2012 Read time: 3 mins
The UK is now benefiting from the installation of sophisticated automated traffic management equipment and information signs on its motorway network.

But with heavy traffic volumes on these roads, novel techniques have had to be implemented. One such operation, organised by client The 2309 Highways Agency and its consulting engineer A.One+, has recently been underway on the M56 motorway between Junctions 9 and 16 in north-west England under the Triple Package Advanced Works designation.

To minimise traffic disturbance, it was decided to use horizontal directional drilling techniques for the majority of the crossing installations for the fibre optic cabling system. Ground investigations were carried out using bore holes at each crossing location and on both sides of the motorway, indicating that this was a suitable trenchless technique for the conditions.

The main contractor for the trenchless installation work was AE Yates, working with sister company AE Yates Trenchless Solutions. The majority of the crossings, 25 out of 26, were completed using various HDD drilling rigs and followed the project plan. The HDD bores varied in length between 40-100m and comprised the installation of four-way 110mm diameter conduits.

However, at one particular crossing location, the work site was restricted in space, both on the launch and reception sides, which meant that the use of the HDD technique was not possible, so another option had to be found.

Investigation of the options available led engineers at 2305 AE Yates to select the pilot auger microtunnelling technique for the limited-space site.

With the auger crossing site comprising compact sand and weathered sandstone, the correct choice of installation technique was vital, while still being able to operate in the confined spaces on either side of the motorway.

Careful consideration of the options available led to the choice of a 2302 Perforator PB85V pilot auger microtunnelling system. The auger crossing comprised the installation of a 45m long, 300mm diameter 'lost steel tube,' which was to act as a carrier pipe for four 110mm diameter conduit pipes supplied by Drain Centre of Wigan, into which the fibre optic cables for the traffic management system would be installed.

To complete the crossing the rig was located in the start shaft on the line and level required for the crossing. As the pilot bore progressed, the use of the laser-based optic electronic navigation system (OEN) allowed the pilot bore to be driven along the required route of the bore towards the target point.

Once the pilot bore was completed the cutting head was changed to an auger system to enlarge the pilot hole, removing spoil with the auger chain installed behind the auger cutting head. With the bore at the correct size the pipe installation was then completed by jacking the necessary pipe into place behind the auger chain while removing the displaced auger units at the reception shaft.

The HDD installations took an average of two restricted-hours night shifts each to complete, because of traffic management constraints, restricted working space and a requirement to dig the HDD rigs in at each site alongside live traffic on the M56 motorway.

Works on the auger crossing installation took five day shifts following shaft construction and site preparation. Using these guided boring systems allowed a tricky project to be completed on a site close to a motorway and in a limited space, a notable achievement.

For more information on companies in this article

Related Content

  • Long reach equipment simplifies demolition
    April 13, 2012
    Demolition is a highly specialised business, as the machinery required to carry out the work on high-rise demolition contracts can be very site specific. Today's high reach demolition rig is no longer simply a tracked excavator with a long boom, indeed some machines cannot be used as excavators at all. Likewise a machine that is dedicated to carrying a 2.5 or 3tonne shear or hammer will need to be built to take the stresses and strains of demolition life. Many of the ultra long boom machines are designed
  • Minnich’s concrete barrier wall drill slides along the barriers
    April 18, 2017
    Minnich Manufacturing, a maker of concrete dowel pin drills, concrete paving vibrators and vibrator monitoring systems, has developed a concrete barrier wall drill. The tool drills vertical holes for the pins used to secure temporary concrete traffic barriers. Minnich, based in Mansfield, Ohio, said the air-driven and self-propelled drill straddles and rides along the top of the temporary wall. A tethered controller enables the operator to simultaneously drill three accurate, consistent pin holes — through
  • Accurate pipe avoidance tool
    January 31, 2017
    PipeHawk says that its improved e-Safe All Service Avoidance Tool reduces the risk of service strikes when carrying out excavation works. The system is said to be more accurate and reliable than a basic cable locator as it does not require a service to be carrying electrical power or providing a discernible electromagnetic field. In fact the service does not even have to be made from a conductive or magnetic material. This allows the system to work equally well on gas and water pipes made from HDPE, MDP
  • Kapsch secures deal for Westgate Tunnel tolling roadside systems
    June 4, 2019
    Kapsch TrafficCom Australia will deliver the tolling roadside system for the West Gate Tunnel Project under construction in Melbourne, Australia. Kapsch TrafficCom Australia was contracted by CPB Contractors John Holland Joint Venture to deliver the technology. It will be based upon the company’s single gantry multilane free-flow platform and next-generation stereoscopic vision technology for both vehicle detection and classification as well as automatic number plate recognition. “Almost 20 years ago Kaps