Motorway's tricky cable installation

The UK is now benefiting from the installation of sophisticated automated traffic management equipment and information signs on its motorway network. But with heavy traffic volumes on these roads, novel techniques have had to be implemented. One such operation, organised by client The Highways Agency and its consulting engineer A.One+, has recently been underway on the M56 motorway between Junctions 9 and 16 in north-west England under the Triple Package Advanced Works designation. To minimise traffic distu
February 6, 2012 Read time: 3 mins
The UK is now benefiting from the installation of sophisticated automated traffic management equipment and information signs on its motorway network.

But with heavy traffic volumes on these roads, novel techniques have had to be implemented. One such operation, organised by client The 2309 Highways Agency and its consulting engineer A.One+, has recently been underway on the M56 motorway between Junctions 9 and 16 in north-west England under the Triple Package Advanced Works designation.

To minimise traffic disturbance, it was decided to use horizontal directional drilling techniques for the majority of the crossing installations for the fibre optic cabling system. Ground investigations were carried out using bore holes at each crossing location and on both sides of the motorway, indicating that this was a suitable trenchless technique for the conditions.

The main contractor for the trenchless installation work was AE Yates, working with sister company AE Yates Trenchless Solutions. The majority of the crossings, 25 out of 26, were completed using various HDD drilling rigs and followed the project plan. The HDD bores varied in length between 40-100m and comprised the installation of four-way 110mm diameter conduits.

However, at one particular crossing location, the work site was restricted in space, both on the launch and reception sides, which meant that the use of the HDD technique was not possible, so another option had to be found.

Investigation of the options available led engineers at 2305 AE Yates to select the pilot auger microtunnelling technique for the limited-space site.

With the auger crossing site comprising compact sand and weathered sandstone, the correct choice of installation technique was vital, while still being able to operate in the confined spaces on either side of the motorway.

Careful consideration of the options available led to the choice of a 2302 Perforator PB85V pilot auger microtunnelling system. The auger crossing comprised the installation of a 45m long, 300mm diameter 'lost steel tube,' which was to act as a carrier pipe for four 110mm diameter conduit pipes supplied by Drain Centre of Wigan, into which the fibre optic cables for the traffic management system would be installed.

To complete the crossing the rig was located in the start shaft on the line and level required for the crossing. As the pilot bore progressed, the use of the laser-based optic electronic navigation system (OEN) allowed the pilot bore to be driven along the required route of the bore towards the target point.

Once the pilot bore was completed the cutting head was changed to an auger system to enlarge the pilot hole, removing spoil with the auger chain installed behind the auger cutting head. With the bore at the correct size the pipe installation was then completed by jacking the necessary pipe into place behind the auger chain while removing the displaced auger units at the reception shaft.

The HDD installations took an average of two restricted-hours night shifts each to complete, because of traffic management constraints, restricted working space and a requirement to dig the HDD rigs in at each site alongside live traffic on the M56 motorway.

Works on the auger crossing installation took five day shifts following shaft construction and site preparation. Using these guided boring systems allowed a tricky project to be completed on a site close to a motorway and in a limited space, a notable achievement.

For more information on companies in this article

Related Content

  • Traffic control solution manufacturers win key project works
    September 26, 2013
    Traffic control system manufacturers have recently supplied some of their cutting-edge technology to major projects in Europe. Meanwhile, in southern Asia, another leading firm in the sector is helping reduce chronic traffic congestion in Indonesia’s capital, Jakarta. Guy Woodford reports Solutions supplied by Siemens Mobility & Logistics (M&L) are helping the Rijkswaterstaat improve traffic conditions at the Coentunnel in Amsterdam, one of the most heavily used traffic arteries in the Netherlands, used
  • Sandvik the key to Raj Stones crushing success
    May 15, 2014
    Raj Stones, based in Fujairah in the United Arab Emirates, is said to have seen its aggregates production increase through the use of a Sandvik Construction CH660 cone crusher. Guy Woodford reports As an operator of one of the larger quarries in the UAE, Raj Stones has used a wealth of Sandvik technology to help reinforce its position as one of the premier aggregate suppliers in the region, now exporting material to Qatar, as well supplying the growing Emirates construction industry. At the heart of t
  • Rockster machines operating in Tanzania extraction operation
    May 14, 2018
    Rockster’s DUPLEX System is being used in an extraction operation in Tanzania. The PB Mining Company in Tanzania selected Rockster’s 2-in-1 machine for crushing highly abrasive rock. The extraction firm was formed in 2014 and specialises in the exploration of lead glance, named Galena, the natural mineral form of lead sulphide. This is the most important ore of lead and usually contains about 1–2% silver, a byproduct that far outweighs the main lead ore in revenue. Because of its low melting point, it is e
  • SWARCO completes installation on UK’s busiest north east highways
    March 22, 2017
    SWARCO has installed a network of 27 variable message signs at some of the busiest highway locations in the northern UK’s Tyneside region. The signs give motorists key information to help them plan their journey and warn them of weather disruption and other potential hazards. Planning and coordinating all works with each local authority was the major challenge, requiring some of the installations to be made in the dead of night. The city of Newcastle was the contracting local authority acting for the Nor