Motorway's tricky cable installation

The UK is now benefiting from the installation of sophisticated automated traffic management equipment and information signs on its motorway network. But with heavy traffic volumes on these roads, novel techniques have had to be implemented. One such operation, organised by client The Highways Agency and its consulting engineer A.One+, has recently been underway on the M56 motorway between Junctions 9 and 16 in north-west England under the Triple Package Advanced Works designation. To minimise traffic distu
February 6, 2012 Read time: 3 mins
The UK is now benefiting from the installation of sophisticated automated traffic management equipment and information signs on its motorway network.

But with heavy traffic volumes on these roads, novel techniques have had to be implemented. One such operation, organised by client The 2309 Highways Agency and its consulting engineer A.One+, has recently been underway on the M56 motorway between Junctions 9 and 16 in north-west England under the Triple Package Advanced Works designation.

To minimise traffic disturbance, it was decided to use horizontal directional drilling techniques for the majority of the crossing installations for the fibre optic cabling system. Ground investigations were carried out using bore holes at each crossing location and on both sides of the motorway, indicating that this was a suitable trenchless technique for the conditions.

The main contractor for the trenchless installation work was AE Yates, working with sister company AE Yates Trenchless Solutions. The majority of the crossings, 25 out of 26, were completed using various HDD drilling rigs and followed the project plan. The HDD bores varied in length between 40-100m and comprised the installation of four-way 110mm diameter conduits.

However, at one particular crossing location, the work site was restricted in space, both on the launch and reception sides, which meant that the use of the HDD technique was not possible, so another option had to be found.

Investigation of the options available led engineers at 2305 AE Yates to select the pilot auger microtunnelling technique for the limited-space site.

With the auger crossing site comprising compact sand and weathered sandstone, the correct choice of installation technique was vital, while still being able to operate in the confined spaces on either side of the motorway.

Careful consideration of the options available led to the choice of a 2302 Perforator PB85V pilot auger microtunnelling system. The auger crossing comprised the installation of a 45m long, 300mm diameter 'lost steel tube,' which was to act as a carrier pipe for four 110mm diameter conduit pipes supplied by Drain Centre of Wigan, into which the fibre optic cables for the traffic management system would be installed.

To complete the crossing the rig was located in the start shaft on the line and level required for the crossing. As the pilot bore progressed, the use of the laser-based optic electronic navigation system (OEN) allowed the pilot bore to be driven along the required route of the bore towards the target point.

Once the pilot bore was completed the cutting head was changed to an auger system to enlarge the pilot hole, removing spoil with the auger chain installed behind the auger cutting head. With the bore at the correct size the pipe installation was then completed by jacking the necessary pipe into place behind the auger chain while removing the displaced auger units at the reception shaft.

The HDD installations took an average of two restricted-hours night shifts each to complete, because of traffic management constraints, restricted working space and a requirement to dig the HDD rigs in at each site alongside live traffic on the M56 motorway.

Works on the auger crossing installation took five day shifts following shaft construction and site preparation. Using these guided boring systems allowed a tricky project to be completed on a site close to a motorway and in a limited space, a notable achievement.

For more information on companies in this article

Related Content

  • New US pavers coming to market
    June 21, 2016
    Key developments are being seen in the market for US pavers, with new models being introduced by several key manufacturers - Mike Woof writes An array of new US-style paver models is now being made available on the market. Several of the main manufacturers have developed updated paver models, with new low emission engines being amongst the key upgrades being fitted. Atlas Copco has new Dynapac pavers available in the shape of its F800T tracked machine as well as the F1000T tracked and F1000W wheeled
  • FlexiPole installed on famous Clifton Bridge
    April 11, 2013
    A number of Ritherdon passively-safe electroluminescent (EL) FlexiPole signpost systems have now been installed on the historic Clifton Suspension Bridge in Bristol, west England. Completed in 1864, the Bridge was originally designed to provide a safe crossing across a gorge for horse-drawn traffic; the chosen method of transport in the 19th century. However it now accommodates 21st century commuter traffic with in excess of 11,000 vehicles crossing the Bridge every day. The custodians of Clifton Suspension
  • Machine control technology shortens road contract
    May 28, 2013
    The use of sophisticated machine control technology has helped halve the schedule required for a road contract – Jeff Winke. By using the latest machine control systems on the equipment fleet, a US contractor has managed to halve worker hours, machine time and overall costs. “We chopped 50% off the contract schedule,” said Jim Swenson, licensed professional land surveyor for Oregon Mainline Paving based in McMinnville, Oregon. “The project was completed a year ahead of the two-year schedule,” he explained
  • Pilosio and CMC Ravenna collaborate on Cornubia Interchange
    June 4, 2019
    The South African branch of the Italian construction company CMC di Ravenna again teamed up with formwork specialist Pilosio to take advantage of Pilosio's solutions. This time it was for construction of a new bridge in the city of Durban, a project named N2/Cornubia Interchange. The overpass will streamline traffic by linking the Umhlanga industrial zone with the Cornubia new development area Tongat. Cornubia is a multibillion rand integrated settlement near Umhlanga, north of Durban, in KwaZulu Natal,