Installation and commissioning process of the Lintec CSD2500B containerised asphalt plant was completed in just one month, including delivery, testing and full operational setup.
By MJ Woof December 9, 2024 Read time: 3 mins
Lintec & Linnhoff has scored a key asphalt plant supply deal to Jordan

Adel Abu Sal & Sons, a leading road construction contractor in Jordan, recently purchased a Lintec CSD2500B containerised asphalt mixing plant supplied by Lintec & Linnhoff’s dealer, Jordan Tractor and Equipment.

The installation and commissioning process of the Lintec CSD2500B plant was completed in just one month, including delivery, testing, and full operational setup, allowing the plant to begin production swiftly. Jordan Tractor is also responsible for plant maintenance to ensure productivity and machine uptime are maintained to the highest possible levels.

The Lintec CSD2500B is being used for three major road construction projects run by the company, with more lined up. The first project started in May 2024 in collaboration with the Greater Amman Municipality and involves the construction of 500,000m2 of roads across the outskirts of Amman. The second project, also with Greater Amman Municipality, began in July 2024 and focuses on 800,000m2 of main road development, with ongoing night shifts to expedite completion. The third project, set to begin in April 2025 for Mafraq Municipality, will cover 250,000m2 of main roads, with completion planned 30 working days after the start.

Transport infrastructure in Jordan is undergoing a huge transformation, with investment opportunities emerging in every sector. These projects are geared towards making the most of Jordan’s growing potential and its prime geographical location as a central transport and logistics corridor for the region.
Installation and commissioning took just one month and, operational since January 2024, the Lintec CSD2500B has produced 80,000tonnes of asphalt to date. This asphalt has been used on a mix of new build and refurbishment highway projects.

Transport remains the lifeblood of the economy in Jordan, connecting the main port in the south with the capital and larger cities in the north. The Lintec CSD2500B has already had a significant impact on this, improving infrastructure and facilitating better connectivity to boost economic activity and enhance the quality of life for the local population.

Tareq Asa’d, Construction Machines sales manager, Jordan Tractor said: “The Lintec CSD2500B asphalt plant offers high productivity, low fuel consumption, and efficient containerised design. These features make it a perfect choice for our road construction projects in Jordan. We’ve been really impressed with it and are considering further purchases as our workload continues to grow.”

The modular design of the Lintec CSD2500B, built i standard containers, lends itself to efficient, economical transportation, and makes the plants ideal for short- and long-term projects. Their flat, rigid design also speeds up installation by eliminating the need for concrete foundations on suitably compacted soil. This asphalt plant features a single lockable main access point for improved onsite security. This containerised concept also means reduced dust and noise emissions.

In addition, Lintec’s novel double screen drum technology eliminates the need for a hot elevator and vibrating screens which in turn reduces maintenance requirements. Combining the heating and screening of the minerals in a single process unit offers significant energy savings. 
 

For more information on companies in this article

Related Content

  • Lintec factory nears completion
    July 5, 2012
    German asphalt and concrete mixing plant manufacturer Lintec has invested some €10 million in a new European factory. The Polish factory in Jasien, near to the German-Polish border, will be ready for operation in February, and will use the latest machinery technology and experienced personnel to produce plants to meet the growing quality demands on the European market.
  • Eurotec plant for port development
    August 2, 2023
    A Japanese contractor bought its second Eurotec ECO60 concrete batching plant, which has been used for a port development project in Madagascar.
  • Lintec showcases redesigned CSD 1500 plant at bauma
    February 12, 2013
    Especially redesigned to allow hot and cold recycling, Lintec will be showcasing its new CSD 1500 asphalt mixing plant at bauma. With a capacity of 120 tonnes/hour, the new CSD 1500 enables the integration of a hot storage silo with a 50tonne capacity. Similar to all Lintec’s CSD line plants, the aggregates enter the screen drum through the front wall.
  • Lintec’s CSM 2500 plant offers low transport costs and quick assembly and disassembly
    January 6, 2017
    Lintec’s new CSM 2500 asphalt mixing plant with parallel drum and conventional screening machine will be on show at bauma. The parallel drum on the plant can be used for hot and cold recycling. Capable of producing 160tonnes/hour, the fully containerised configuration of the CSM 2500 is said by its German manufacturer to ensure lower transport costs and quick and efficient assembly and disassembly. The plant has six screening decks, a 60tonne capacity hot stone bin, a 45tonne reclaimed filler silo, produces