Kieswerk Kohler solves fines problem with M2500 from CDE

Following installation of the M2500 mobile washing plant, Kieswerk Kohler is said to have addressed the issues caused by excess fines in the material at their quarry in Engen / Welschingen, southern Germany. The solution offered by CDE has also enabled the production of an additional sand product which the company is now able to offer customers. The raw material processed by Kieswerk Kohler at the site contains a large proportion of material smaller than 250 microns. With the crushing and screening proce
September 26, 2013 Read time: 4 mins
Following installation of the M2500 mobile washing plant, Kieswerk 2278 Kohler is said to have addressed the issues caused by excess fines in the material at their quarry in Engen / Welschingen, southern Germany. The solution offered by 3168 CDE Global has also enabled the production of an additional sand product which the company is now able to offer customers.

The raw material processed by Kieswerk Kohler at the site contains a large proportion of material smaller than 250 microns. With the crushing and screening processes previously employed on the material, the sand was out of specification for use in concrete. “This was causing a problem as local concrete manufacturers are my main customers,” explained owner Thomas Kohler. “I had been working to develop a system which would allow production of concrete aggregates, especially sand, so that it would meet the requirements of the European standards. The solution offered by CDE has also enabled the production of an additional saleable sand product which I can now offer customers.”

CDE in Heimertingen was formed in December 2012 and represents a development of the previous distributor agreement that was in place for southern Germany with Jurgen Koelsch. Stefan Koelsch director of CDE said, “CDE gives washing a new focus in Germany. This ensures that we are able to offer aggregate and construction material manufacturers a level of washing expertise, as well as project management capability and service support that is only available when construction materials producers buy direct from the manufacturer.”

In seeking to address the issues raised by the large proportion of minus 250 micron material in the sand and gravel feed, Kieswerk Kohler were investigating the option of washing the material after the initial dry screening process. “We were thinking about several different options and ways in which we could correct the gradation curve of the sand in order that it met the required concrete specification,” said Kohler. “When we explained the issue to CDE they came up with a solution very quickly and, since it has been introduced, the plant is doing exactly what I wanted it to do.”

The processing system introduced by CDE in Baden-Wurttemberg includes the M2500 E4 mobile washing plant and the AggMax 83 portable logwasher. In addition to the problems caused by the excess fines content in the feed material, Kieswerk Kohler were also faced with clays and silts which the dry processing system was not able to effectively remove. The consultation between Thomas Kohler and Stefan Kolsch revealed that by introducing the AggMax the quality of aggregates produced would also be improved.

The sand and gravel feed is delivered to the M2500 washing plant by loading shovel and operates at 100tonnes/hour. The plant accepts 0-100mm material with a grid on the feed hopper rejecting any oversize. The feed material is then delivered to the M2500 aggregate screening phase which is achieved using the integrated Prograde P2-75 rinsing screen.

The top deck of this screen separates at +32mm and this material is sent to stockpile via one of the integrated wing conveyors. The bottom deck separates at 4-32mm and this material is then sent to the AggMax for scrubbing via the integrated Rotomax RX80 logwasher. Once material has been processed by the Rotomax it is discharged onto a triple deck horizontal sizing screen which classifies the aggregates into 4-8mm, 8-16mm and 16-32mm.

The 0-4mm material collects in the Prograde screen sump and is pumped to the integrated Evowash sand washing plant. The Evowash screen is split to allow the production of two sand grades – 0-4mm concrete sand and another 0-2mm product. “The creation of the additional 0-2mm sand product was required as there was too much of this material in the 0-4mm range. The sand washing phase is configured to remove up to 25% of the 0-2mm material from the 0-4mm product to allow for the production of concrete sand,” said Koelsch.

An additional benefit for Kieswerk Kohler has been the creation of this 0-2mm sand product which they have now found a market for.

As well as selling the final washed products to local concrete manufacturers in Germany some material is also exported into Switzerland due to the proximity of the Kieswerk Kohler site to the Swiss border.

For more information on companies in this article

Related Content

  • Recycling option
    February 22, 2012
    Roadtec is offering a new cold recycling machine, the RT-500, aimed at duties in projects using the recycling train concept. Electrically powered by a Cat C9 generator set, the RT-500 can handle up to 600 tonnes/hour of material and is designed to crush and screen the recycled asphalt pavement (RAP) produced by an RX-900 cold planer. It has a JCI double deck screen that sorts milled material provided by the RX-900's conveyor. Any oversized material is fed back into the RT-500's Telsmith 3048 impact crusher
  • Construction future for CEA
    July 18, 2012
    The UK’s Construction Equipment Association plays a key role in Europe - Mike Woof writes The UK’s Construction Equipment Association (CEA) is playing an important role within Europe, for manufacturers, customers and also for the wider benefit of industry as a whole. One important project where the CEA is closely involved with other sister organisations within the pan-European organisation CECE is with the rationalisation of machine regulations. Requirements were supposed to have been harmonised in 1992, an
  • Marini mobility option
    June 4, 2019
    Marini is offering new versions of its Xpress plant. The first version was the Xpress 2500, but the range is now being widened with the addition of the Xpress 1500, 1500P, 2000 and 2000P models. Andrea Zanoletti is in charge of this range and explained that the plants are designed for maximum mobility. He said, “With only two trailers, you have a complete asphalt plant.” The existing Xpress 2500 model offers an output of up to 250tonnes/hour. However, the new Xpress 1500 and 1500P offer outputs of 150
  • Liebherr’s new mixing plant generation
    October 11, 2022
    Liebherr is introducing a new mixing plant generation, with modular design being a key feature. The new generation plants will be available in Germany, Austria and Switzerland from 2023, and will then be made available for world markets.