Kieswerk Kohler solves fines problem with M2500 from CDE

Following installation of the M2500 mobile washing plant, Kieswerk Kohler is said to have addressed the issues caused by excess fines in the material at their quarry in Engen / Welschingen, southern Germany. The solution offered by CDE has also enabled the production of an additional sand product which the company is now able to offer customers. The raw material processed by Kieswerk Kohler at the site contains a large proportion of material smaller than 250 microns. With the crushing and screening proce
September 26, 2013 Read time: 4 mins
Following installation of the M2500 mobile washing plant, Kieswerk 2278 Kohler is said to have addressed the issues caused by excess fines in the material at their quarry in Engen / Welschingen, southern Germany. The solution offered by 3168 CDE Global has also enabled the production of an additional sand product which the company is now able to offer customers.

The raw material processed by Kieswerk Kohler at the site contains a large proportion of material smaller than 250 microns. With the crushing and screening processes previously employed on the material, the sand was out of specification for use in concrete. “This was causing a problem as local concrete manufacturers are my main customers,” explained owner Thomas Kohler. “I had been working to develop a system which would allow production of concrete aggregates, especially sand, so that it would meet the requirements of the European standards. The solution offered by CDE has also enabled the production of an additional saleable sand product which I can now offer customers.”

CDE in Heimertingen was formed in December 2012 and represents a development of the previous distributor agreement that was in place for southern Germany with Jurgen Koelsch. Stefan Koelsch director of CDE said, “CDE gives washing a new focus in Germany. This ensures that we are able to offer aggregate and construction material manufacturers a level of washing expertise, as well as project management capability and service support that is only available when construction materials producers buy direct from the manufacturer.”

In seeking to address the issues raised by the large proportion of minus 250 micron material in the sand and gravel feed, Kieswerk Kohler were investigating the option of washing the material after the initial dry screening process. “We were thinking about several different options and ways in which we could correct the gradation curve of the sand in order that it met the required concrete specification,” said Kohler. “When we explained the issue to CDE they came up with a solution very quickly and, since it has been introduced, the plant is doing exactly what I wanted it to do.”

The processing system introduced by CDE in Baden-Wurttemberg includes the M2500 E4 mobile washing plant and the AggMax 83 portable logwasher. In addition to the problems caused by the excess fines content in the feed material, Kieswerk Kohler were also faced with clays and silts which the dry processing system was not able to effectively remove. The consultation between Thomas Kohler and Stefan Kolsch revealed that by introducing the AggMax the quality of aggregates produced would also be improved.

The sand and gravel feed is delivered to the M2500 washing plant by loading shovel and operates at 100tonnes/hour. The plant accepts 0-100mm material with a grid on the feed hopper rejecting any oversize. The feed material is then delivered to the M2500 aggregate screening phase which is achieved using the integrated Prograde P2-75 rinsing screen.

The top deck of this screen separates at +32mm and this material is sent to stockpile via one of the integrated wing conveyors. The bottom deck separates at 4-32mm and this material is then sent to the AggMax for scrubbing via the integrated Rotomax RX80 logwasher. Once material has been processed by the Rotomax it is discharged onto a triple deck horizontal sizing screen which classifies the aggregates into 4-8mm, 8-16mm and 16-32mm.

The 0-4mm material collects in the Prograde screen sump and is pumped to the integrated Evowash sand washing plant. The Evowash screen is split to allow the production of two sand grades – 0-4mm concrete sand and another 0-2mm product. “The creation of the additional 0-2mm sand product was required as there was too much of this material in the 0-4mm range. The sand washing phase is configured to remove up to 25% of the 0-2mm material from the 0-4mm product to allow for the production of concrete sand,” said Koelsch.

An additional benefit for Kieswerk Kohler has been the creation of this 0-2mm sand product which they have now found a market for.

As well as selling the final washed products to local concrete manufacturers in Germany some material is also exported into Switzerland due to the proximity of the Kieswerk Kohler site to the Swiss border.

For more information on companies in this article

Related Content

  • Modern formwork systems - fast, flexible, safe
    February 21, 2012
    Speed of erection, safety, cost-efficiency and flexibility are among the attributes of modern formwork systems. Modern formwork and scaffolding systems are attractive in particular for their speed of erection, safety, cost-efficiency and flexibility.
  • Raised dual carriageway reduces congestion
    February 21, 2012
    A new raised dual carriageway to bypass the historic centre of the City of Wroclaw in south-east Poland will give access to the new Miejski Stadium in time for its role in the UEFA Euro 2012 football finals.
  • Concrete paving developments boosting performance
    April 12, 2018
    Change is afoot at Miller Formless following its change of ownership, with investment in research and design a priority – Mike Woof writes Miller Formless is undergoing a process of change under its new ownership, with investment in the factory as well as in the product range. The recent tie-up between Guntert & Zimmerman and Miller Formless has brought additional global manufacturing capacity. Guntert & Zimmerman had established a manufacturing presence in India through an agreement with a local firm, a
  • Terex Washing Systems highlight new AggreSand 206 wash plant at INTERMAT 2015
    January 6, 2017
    Terex Washing Systems is here this week highlighting the successful launch of its new AggreSand 206 wash plant. Capable of handling up to 400tonnes per hour of material, the AggreSand 206 is suitable for all industrial, construction, recycling and mining applications. The first AggreSand 206 wash plant has been installed in the UK at the new Lafarge Tarmac site in Bedfordshire, England, where it is working alongside an AggreScrub 150. There are a number of other installations planned globally. “Th