Skip to main content

Intelligent monitoring of concrete pours cuts time on site

Intelligent monitoring of concrete strengths is helping contractors shave weeks off construction programmes, according to formwork specialist Doka. Its Concremote system measures the temperature of the concrete, converts that to predicted strength and allows the contractor to strike the formwork when the concrete is ready – rather than waiting for a set number of days. “Concretemote is being used on 20 to 25 projects,” said Doka’s director of research and development Johann Peneder.
April 12, 2016 Read time: 2 mins
The Concremote concrete monitor can allow contractors to strike forms earlier

Intelligent monitoring of concrete strengths is helping contractors shave weeks off construction programmes, according to formwork specialist 203 Doka. Its Concremote system measures the temperature of the concrete, converts that to predicted strength and allows the contractor to strike the formwork when the concrete is ready – rather than waiting for a set number of days.

“Concretemote is being used on 20 to 25 projects,” said Doka’s director of research and development Johann Peneder. “In some countries we cannot fully use the advantages of Concremote due to the regulations, which are based on previous experience, but this is the first steps towards employing techniques which will give a more efficient and economical way to build.”

The latest development of the Concremote system will see formwork panels with ready-made positions for the Concremote sensor to plug into - currently it sits on top of the concrete pour. Called Concremote plug.IN, this addition will allow faster and more flexible monitoring of concrete strengths, Peneder added.

“Contractors can use products such as Concemote for long-term quality monitoring of the job sit,” he continued. “They can then add that data into the BIM model and can transfer that data to the owner.”

One of Concremote’s current applications demonstrates its benefits in countries with huge climatic variation. On Canada’s Muskrat Falls hydro power project, where temperatures can fall to minus 40degrees C, it has allowed earlier striking of forms but also ongoing monitoring of the concrete after striking. This allows the contractor to protect the concrete where necessary to avoid temperature shock - between the hot concrete and cold outside - and hence prevent damage.

All videos

For more information on companies in this article

Related Content

  • New CEO plans global expansion for Pilosio
    April 15, 2016
    The new CEO of Pilosio, Johann Strunz, has some ambitious expansion plans for the euro45m-turnover company. The former managing director of Doka’s Austrian business plans to decentralise the Italian formwork and falsework specialist, with hubs in various regions in addition to its Italian headquarters. “We are moving from being a head-quartered company to a decentralised structure,” said Strunz. “We want to give power to the markets. They will decide on the pace and the headquarters will define the quali
  • Lochkov bridge construction time 'cut'
    July 17, 2012
    As part of the R1 southern orbital motorway around the Czech capital, Prague, a joint venture is building a five-span, 461m long and approximately 65m high viaduct near the village of Lochkov, as a girder bridge construction. For the two steeply inclined twin piers, Doka has supplied an automatic climbing formwork solution that obviates the need for shoring and that will "cut more than 100 days from the construction period." Cast-in-place concrete construction of bridge piers with such a steep inclination
  • Far from formulaic
    January 4, 2013
    Formwork solutions for the first axial suspension cable stayed bridge in India; and a four-lane road bridge in Germany’s Harz Mountains, are among the latest bridge-based formwork projects analysed by Guy Woodford. RMD Kwikform India has won the contract to design and supply shoring and formwork solutions for the first axial suspension cable stayed bridge ever built in India. The Kota Bridge’s innovative design sees a single 350m span cross the entire width of the Chambal River, with three approach spans on
  • Trimble is developing smart construction site solutions
    March 7, 2016
    Trimble is taking the concept of the building information model (BIM) one stage further with its development of its construction continuum concept. This is intended to show the process and benefits to building a construction-ready model embedded with intelligent data. Such a model can serve as the basis for how contractors plan and execute construction projects. With intelligent modeling, users can add and remove information in real time while simultaneously looking at multiple ways to perform construction