Intelligent monitoring of concrete pours cuts time on site

Intelligent monitoring of concrete strengths is helping contractors shave weeks off construction programmes, according to formwork specialist Doka. Its Concremote system measures the temperature of the concrete, converts that to predicted strength and allows the contractor to strike the formwork when the concrete is ready – rather than waiting for a set number of days. “Concretemote is being used on 20 to 25 projects,” said Doka’s director of research and development Johann Peneder.
April 12, 2016 Read time: 2 mins
The Concremote concrete monitor can allow contractors to strike forms earlier

Intelligent monitoring of concrete strengths is helping contractors shave weeks off construction programmes, according to formwork specialist 203 Doka. Its Concremote system measures the temperature of the concrete, converts that to predicted strength and allows the contractor to strike the formwork when the concrete is ready – rather than waiting for a set number of days.

“Concretemote is being used on 20 to 25 projects,” said Doka’s director of research and development Johann Peneder. “In some countries we cannot fully use the advantages of Concremote due to the regulations, which are based on previous experience, but this is the first steps towards employing techniques which will give a more efficient and economical way to build.”

The latest development of the Concremote system will see formwork panels with ready-made positions for the Concremote sensor to plug into - currently it sits on top of the concrete pour. Called Concremote plug.IN, this addition will allow faster and more flexible monitoring of concrete strengths, Peneder added.

“Contractors can use products such as Concemote for long-term quality monitoring of the job sit,” he continued. “They can then add that data into the BIM model and can transfer that data to the owner.”

One of Concremote’s current applications demonstrates its benefits in countries with huge climatic variation. On Canada’s Muskrat Falls hydro power project, where temperatures can fall to minus 40degrees C, it has allowed earlier striking of forms but also ongoing monitoring of the concrete after striking. This allows the contractor to protect the concrete where necessary to avoid temperature shock - between the hot concrete and cold outside - and hence prevent damage.

All videos

For more information on companies in this article

Related Content

  • New concrete testing technologies improve speed, safety and quality
    July 8, 2016
    Developments in data processing and management are revolutionising the way concrete strengths can be measured and used to improve efficiencies - Kristina Smith reports on two new technologies A new system that uses thermal imaging to measure the strength of sprayed concrete tunnel linings is being trialled for the first time in London. The brainchild of Dr Benoit Jones, managing director of Inbye Engineering, the technique could lead to improvements in safety, quality and – in the longer run – productivi
  • Doka’s Concremote gives exact measurement for accurate control
    March 3, 2016
    Doka’s Concremote makes it possible to measure concrete strength on the site and in real time. It uses the weighted maturity method, as developed by de Vree, to provide reliable, standards-compliant information on the strength development of the concrete. This facilitates targeted management of the forming and CIP concreting operations. The advantage of the method is the measurement take place directly in the concrete element. With well-placed sensors - thermos-couples - the temperature can easily be mea
  • Doka’s Concremote gives exact measurement for accurate control
    January 6, 2017
    Doka’s Concremote makes it possible to measure concrete strength on the site and in real time. It uses the weighted maturity method, as developed by de Vree, to provide reliable, standards-compliant information on the strength development of the concrete. This facilitates targeted management of the forming and CIP concreting operations. The advantage of the method is the measurement take place directly in the concrete element. With well-placed sensors - thermos-couples - the temperature can easily be mea
  • Doka’s UniKit is a quick way to support heavy concrete pours
    April 19, 2016
    Doka’s new UniKit is a modular shoring system for heavy civil engineering applications. Designed to be quick and easy to erect in a number of different configurations, UniKit provides a steel-girder like structure which can support loads from bridge deck or beam concrete pours. “It’s an efficient way to construct infrastructure without stopping existing infrastructure – such as roads – running underneath,” said Doka’s director of research and development Johann Peneder.