HA dismantles footbridge over M5 in England

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England. The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane. The dismantling and removal of the
January 3, 2013 Read time: 2 mins

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England.

The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane.

The dismantling and removal of the 220tonne bridge required the M5 being closed in both directions for the duration of the work, from 7pm on Saturday 10 November until around 8am the following morning, when both carriageways were fully opened.
The bridge was dismantled into two sections, each of which was hoisted and removed by cranes. This method of removal was required to avoid excessive vibration due to the presence of a pipeline on the northbound carriageway.

The new pedestrian bridge is planned to be in place and available for use by early 2013.

2309 Highways Agency project manager Paul Unwin said: “The removal of the old bridge is an essential part of the managed motorway scheme, and the closures meant that our workers were able to concentrate on doing a fantastic job in dismantling the structure as quickly and as safely as possible.”

Once completed, the €109.72 million (£88mn) managed motorway scheme will cut congestion, make journey times more reliable and improve safety through the use of variable mandatory speed limits and by opening the hard shoulder as an extra running lane. 

For more information on companies in this article

Related Content

  • UK’s M3 motorway gets first orange smart motorway emergency area
    July 19, 2017
    The first of a new-style smart motorway emergency stop area is being trialled on the M3 in England’s county Surrey. The redesigned emergency area has a highly visible orange road surface and better signs to help improve its visibility make it more obvious to drivers on smart motorways, according to Highways England.
  • UK death rate not falling fast enough in The Reported Road Casualties Great Britain Report 2013
    September 26, 2014
    Road safety lobby groups have criticised Britain for pushing down its annual road fatality rate by a further 2% in the past year, the lowest figure since records began in 1926. The Reported Road Casualties Great Britain 2013 (RRCGB) Annual Report, published in September 2014, reveals that 1,713 people were killed in road accidents in the country during 2013, with the number of people seriously injured down by 6% to 21,657 versus 2012.
  • Upgrade work starts on junction of London’s orbital motorway M25
    February 20, 2015
    Work has started on a €136 million road improvement project on the UK’s London ring road, the M25 motorway. Crews from Balfour Beatty and Skanska have moved onto the interchange between the A13 national road and the M25 at junction 30 near Thurrock in the county Essex. The A13 on approach to the junction will be widened to four lanes in each direction and the junction itself will have dedicated link roads between the M25 and the A13. “Traffic at the junction is expected to grow by up to a quarter b
  • Costain completes Cornish construction project
    August 2, 2024
    Costain has completed a key Cornish construction project.