Skip to main content

HA dismantles footbridge over M5 in England

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England. The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane. The dismantling and removal of the
January 3, 2013 Read time: 2 mins

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England.

The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane.

The dismantling and removal of the 220tonne bridge required the M5 being closed in both directions for the duration of the work, from 7pm on Saturday 10 November until around 8am the following morning, when both carriageways were fully opened.
The bridge was dismantled into two sections, each of which was hoisted and removed by cranes. This method of removal was required to avoid excessive vibration due to the presence of a pipeline on the northbound carriageway.

The new pedestrian bridge is planned to be in place and available for use by early 2013.

2309 Highways Agency project manager Paul Unwin said: “The removal of the old bridge is an essential part of the managed motorway scheme, and the closures meant that our workers were able to concentrate on doing a fantastic job in dismantling the structure as quickly and as safely as possible.”

Once completed, the €109.72 million (£88mn) managed motorway scheme will cut congestion, make journey times more reliable and improve safety through the use of variable mandatory speed limits and by opening the hard shoulder as an extra running lane. 

For more information on companies in this article

Related Content

  • TRL delivers its vision
    July 31, 2012
    The UK's world-renowned TRL (Transport Research Laboratory) is celebrating its 75th birthday this year, and the objective of its work has not changed In 1938 Richard Stradling, director, wrote that "the objective of all the research work at RRL [now TRL] is to accumulate that body of scientific knowledge which is an essential factor in the economical and efficient construction and maintenance of our roads. Practical application of the results must be the aim throughout." While TRL's remit today is far more
  • Faithful+Gould in England highway efficiencies
    July 8, 2022
    Faithful+Gould - a member of the SNC-Lavalin Group - will deal with issues around safety, congestion and road capacity.
  • England road upgrades planned
    June 14, 2021
    A road upgrade programme is planned for the East of England.
  • High speed bridge demolition minimises disruption
    February 16, 2012
    A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.