HA dismantles footbridge over M5 in England

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England. The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane. The dismantling and removal of the
January 3, 2013 Read time: 2 mins

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England.

The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane.

The dismantling and removal of the 220tonne bridge required the M5 being closed in both directions for the duration of the work, from 7pm on Saturday 10 November until around 8am the following morning, when both carriageways were fully opened.
The bridge was dismantled into two sections, each of which was hoisted and removed by cranes. This method of removal was required to avoid excessive vibration due to the presence of a pipeline on the northbound carriageway.

The new pedestrian bridge is planned to be in place and available for use by early 2013.

2309 Highways Agency project manager Paul Unwin said: “The removal of the old bridge is an essential part of the managed motorway scheme, and the closures meant that our workers were able to concentrate on doing a fantastic job in dismantling the structure as quickly and as safely as possible.”

Once completed, the €109.72 million (£88mn) managed motorway scheme will cut congestion, make journey times more reliable and improve safety through the use of variable mandatory speed limits and by opening the hard shoulder as an extra running lane. 

For more information on companies in this article

Related Content

  • Airport's high demands on asphalt and concrete techniques
    July 11, 2012
    Airport runway, taxiway and parking areas make high demands on paving requirements, both with concrete and asphalt techniques. Mike Woof reports. High quality surface finishes are required in airport environments for runways, taxiways and aircraft parking areas. Because of the speed at which aircraft take off and land and the massive forces exerted due to the weight of the aircraft, particularly during landing, runway structures need to be incredibly strong. The surfaces also have to be constructed to very
  • Towers of power: California’s Gerald Desmond Bridge Replacement
    May 8, 2019
    Challenging ground conditions meant a design rethink - and some engineering firsts - for California’s Gerald Desmond Bridge Replacement Project* The Port of Long Beach on Terminal Island south of Los Angeles is the second-busiest container port in the US. It handles around 15% of all imported goods, much of it with Asia. As the Port of Long Beach was growing in importance over the past half century, the 51-year-old Gerald Desmond Bridge has faithfully been delivering thousands of daily commuters to wo
  • Peri cantilever for Terfener Bridge
    February 26, 2021
    Peri used its VBC Balanced Cantilever Carriage for the first time in Central Europe.
  • Towards sustainable mobility
    April 12, 2012
    Tony Marshall, Director at Arup, looks at ways in which the company encourages sustainable mobility.From policy and systems development through to the design and execution of major infrastructure projects, he reviews Arup's global project experiences and research programmes. Space on roads throughout the modern world is decreasing as the volume of cars and road users increases. How can mobility be safeguarded without compromising quality of life or environmental well-being? As engineers, we have a responsib