HA dismantles footbridge over M5 in England

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England. The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane. The dismantling and removal of the
January 3, 2013 Read time: 2 mins

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England.

The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane.

The dismantling and removal of the 220tonne bridge required the M5 being closed in both directions for the duration of the work, from 7pm on Saturday 10 November until around 8am the following morning, when both carriageways were fully opened.
The bridge was dismantled into two sections, each of which was hoisted and removed by cranes. This method of removal was required to avoid excessive vibration due to the presence of a pipeline on the northbound carriageway.

The new pedestrian bridge is planned to be in place and available for use by early 2013.

2309 Highways Agency project manager Paul Unwin said: “The removal of the old bridge is an essential part of the managed motorway scheme, and the closures meant that our workers were able to concentrate on doing a fantastic job in dismantling the structure as quickly and as safely as possible.”

Once completed, the €109.72 million (£88mn) managed motorway scheme will cut congestion, make journey times more reliable and improve safety through the use of variable mandatory speed limits and by opening the hard shoulder as an extra running lane. 

For more information on companies in this article

Related Content

  • Carillion wins UK M6 managed motorway contract
    May 3, 2012
    Carillion has been awarded a US$16 million contract to transform another section of the UK’s M6 in Birmingham, between Junctions 5 and 8, into a managed motorway.
  • Carillion wins UK M6 managed motorway contract
    March 22, 2012
    Carillion has been awarded a US$16 million contract to transform another section of the UK’s M6 in Birmingham, between Junctions 5 and 8, into a managed motorway.
  • Busy bridge in Beijing replaced quickly
    March 31, 2016
    The replacement of a very busy road bridge in China’s capital Beijing has been carried out successfully. Due to the volume of traffic using the bridge during week days, the work had to be carried out quickly so as to minimise traffic disruption. But despite being carried out in the centre of Beijing, the replacement work for the Sanyuan Bridge just took 43 hours from start to completion.
  • Europe closes in on the crossings
    September 27, 2017
    The Mersey Gateway bridge project off England’s west coast passed a milestone recently with the first joining of two of the deck sections. The key segments, as the sections are called, link the north approach viaduct to the north pylon deck span and are the first of four deck-joins scheduled for this summer. In total, there are five sections of bridge deck and approach roads that need to be joined.