Eurovia races against the clock for London’s Race of Champions

Fast-track construction has taken on a new meaning following the successful staging of the Race of Champions in London’s Olympic Stadium. The knockout tournament for the world’s best drivers – won by Formula 1 driver Sebastian Vettel – required a super-fast construction and dismantling of a safe, high-speed circuit within the Queen Elizabeth Olympic Stadium. Eurovia UK had just four weeks to design the track, complete trials and mobilise for the project following the contract award. The circuit was co
June 17, 2016 Read time: 2 mins
And the winner is Eurovia UK
Fast-track construction has taken on a new meaning following the successful staging of the Race of Champions in London’s Olympic Stadium.

The knockout tournament for the world’s best drivers – won by Formula 1 driver Sebastian Vettel – required a super-fast construction and dismantling of a safe, high-speed circuit within the Queen Elizabeth Olympic Stadium. 3281 Eurovia UK had just four weeks to design the track, complete trials and mobilise for the project following the contract award.

The circuit was constructed in one week, allowing organisers three days for driving practice ahead of the event last November. Afterwards, the project team had 36 hours to remove the track, but accomplished this in just 25 hours.

Eurovia contracting business manager Dave Boswell said tight control of logistics was essential, given the complexity of the project and constraints on Eurovia’s access to the stadium.

Working in conjunction with the Race of Champions team, the track was designed by technical consultancy 2374 Jean Lefebvre (UK). It was constructed with recycled road planings laid on aluminium trackway panels to protect the pitch’s underground heating. The 150mm base layer was then overlaid with SMA binder and a thin surface course paved in Echelon.

Sims Milling & Eurovia Roadstone processed the materials after laying trials at its Bull Lodge quarry in Essex. Conventional wheeled, tracked and midi-pavers were used to lay different grades of planings. Sims Milling also demonstrated that the material could be removed by cold milling without damaging the aluminium plates.

Around 3,000tonnes of road planings and 1,800tonnes of asphalt were used in the construction of the 8,000m2 circuit. It required 1,000 plates provided by Davis Trackway, which played a similar role for the opening ceremony of the 2012 Olympics.

For more information on companies in this article

Related Content

  • Asphalt reinforcement extends road life
    July 12, 2012
    Special reinforcements can extend the life of an old or new road, and also offer environmental benefits. Patrick Smith reports. Asphalt reinforcement can extend the service life of a resurfaced road by a factor of 3-4, says Huesker, developers of the HaTelit range of asphalt reinforcement. Aimed at preventing the propagation of reflective cracking from an old asphalt layer through a new surface course, Huesker claims the formation of reflective cracking is considerably delayed or even completely prevented u
  • Reduced emissions, costs, with recycled asphalt
    February 21, 2012
    Recycling is a key issue for asphalt road construction, with many technologies now coming to market. Bith an ever increasing emphasis on sustainability forcing change in the construction sector in Europe and North America, the highway sector now has to seek new solutions.
  • High speed highway repair
    February 29, 2012
    A high speed highway rehabilitation has seen the repaving of a 1.5km stretch of road in just two night shifts. A Vögele SUPER 1800-2 paver fitted with one of the firm's SprayJet modules helped boost productivity and cut operating costs for Dutch contractor MNO Vervat.
  • Airport's high demands on asphalt and concrete techniques
    July 11, 2012
    Airport runway, taxiway and parking areas make high demands on paving requirements, both with concrete and asphalt techniques. Mike Woof reports. High quality surface finishes are required in airport environments for runways, taxiways and aircraft parking areas. Because of the speed at which aircraft take off and land and the massive forces exerted due to the weight of the aircraft, particularly during landing, runway structures need to be incredibly strong. The surfaces also have to be constructed to very