Eurovia races against the clock for London’s Race of Champions

Fast-track construction has taken on a new meaning following the successful staging of the Race of Champions in London’s Olympic Stadium. The knockout tournament for the world’s best drivers – won by Formula 1 driver Sebastian Vettel – required a super-fast construction and dismantling of a safe, high-speed circuit within the Queen Elizabeth Olympic Stadium. Eurovia UK had just four weeks to design the track, complete trials and mobilise for the project following the contract award. The circuit was co
June 17, 2016 Read time: 2 mins
And the winner is Eurovia UK
Fast-track construction has taken on a new meaning following the successful staging of the Race of Champions in London’s Olympic Stadium.

The knockout tournament for the world’s best drivers – won by Formula 1 driver Sebastian Vettel – required a super-fast construction and dismantling of a safe, high-speed circuit within the Queen Elizabeth Olympic Stadium. 3281 Eurovia UK had just four weeks to design the track, complete trials and mobilise for the project following the contract award.

The circuit was constructed in one week, allowing organisers three days for driving practice ahead of the event last November. Afterwards, the project team had 36 hours to remove the track, but accomplished this in just 25 hours.

Eurovia contracting business manager Dave Boswell said tight control of logistics was essential, given the complexity of the project and constraints on Eurovia’s access to the stadium.

Working in conjunction with the Race of Champions team, the track was designed by technical consultancy 2374 Jean Lefebvre (UK). It was constructed with recycled road planings laid on aluminium trackway panels to protect the pitch’s underground heating. The 150mm base layer was then overlaid with SMA binder and a thin surface course paved in Echelon.

Sims Milling & Eurovia Roadstone processed the materials after laying trials at its Bull Lodge quarry in Essex. Conventional wheeled, tracked and midi-pavers were used to lay different grades of planings. Sims Milling also demonstrated that the material could be removed by cold milling without damaging the aluminium plates.

Around 3,000tonnes of road planings and 1,800tonnes of asphalt were used in the construction of the 8,000m2 circuit. It required 1,000 plates provided by Davis Trackway, which played a similar role for the opening ceremony of the 2012 Olympics.

For more information on companies in this article

Related Content

  • Maputo Airport runway rebuild
    March 26, 2019
    Rebuilding work has been carried out on the runway and taxiways at Maputo International Airport in Mozambique. The work was carried out for Aeroportos de Moçambique, with the engineering handled by NACO and US$64 million of funding being suplied by Agence Française de Dévelopement.
  • Ringway nears the end of a 300km road marking project in Hertfordshire
    December 11, 2015
    Highways contractor Ringway is nearly finished refreshing more than 300km of road markings for Hertfordshire County Council, north of London, in the United Kingdom. Two road marking crews consisting of two operatives have been working since April and are due to finish this month. They have been working predominantly at night to minimise disruption to the travelling public. Work is prioritised based on national road hierarchy - A, B, C and unclassified roads, said Kevin Carrol, Ringway’s Hertfordshire div
  • Wirtgen milling machines and soil stabilisers land in Sardina
    July 26, 2016
    Wirtgen cold milling machines recently demonstrated their ability on runway rehabilitation work at Alghero-Fertilia Airport in Sardinia. Alghero-Fertilia Airport, about 8km northwest of Alghero, is one of three commercial airports on the Italian island. Built as a military airport in the late 1930s, Alghero-Fertilia still occasionally serves this purpose today. It is also a major hub for low-cost carriers that ferry many of the annual 1.7 million passengers who pass through the airport. Summer tourist mo
  • Speedy airport upgrade
    February 15, 2012
    Increases in flight numbers from the Frankfurt Hahn airport have resulted in necessary improvements to the facility, including new runway surfaces. The former German military airbase has been used as a civilian airport since 1993 but is now Germany's fifth largest air cargo hub and handles some 40,000 flights/year.