Climbing in Corpus Christi

The challenge for Doka on the new Harbor Bridge in Texas was to use the same formwork for each pylon despite each pylon’s different geometry.
September 17, 2020 Read time: 2 mins
Doka used its hydraulic climbing formworks SKE50 and SKE100 plus its large-area formwork Top 50

The new US 181 Harbor Bridge is being constructed to replace an ageing bridge across the Corpus Christi Ship Channel off the Gulf of Mexico. The replacement bridge, with nearly a 63m clearance, will also allow the passage of larger ships and possibly cruise ships into the docks. The current Harbor Bridge was opened in 1956 to replace a drawbridge and now handles 26,000 vehicles per day. When complete, the new Harbor Bridge will be the tallest point in southern Texas and the longest cable-stayed concrete segmental bridge in the US.

The upper and lower pylons were different shapes requiring two designs. The primary pylon structures have a geometry that narrows and angles at the same time. A reusable system was needed that would have minimal changes between pours.

Doka used large-area formwork Top 50 as well as hydraulic climbing formwork SKE50 and SKE100 platforms. The system was designed with telescopic platforms that adjust to the changing pylon shape. Doka says there were almost 520m² of formwork for one pylon.

Doka helped the contractor – a Flatiron and Dragados joint venture - remain on schedule because there was minimal rebuild between pours. Doka also saved crane time due to the hydraulic lifting systems employed.

The contract won by Flatiron and Dragados includes $854.6 million for design and construction of the bridge and another $128.2 million for the 25-year maintenance and operation of the bridge.

For more information on companies in this article

Related Content

  • Nigeria’s giant city Lagos to benefit from a new cable-stayed bridge
    September 19, 2012
    The first cable-stayed bridge in Nigeria will link two districts of the megacity of Lagos Nigeria’s first cable-stayed bridge, the Lekki Ikoyi Bridge in the megacity of Lagos is scheduled for completion at the end of 2012. Its striking 90m high pylon characterises the appearance of the 1,357m long bridge, which will connect two districts of the West African city, Lekki on the Lekki Peninsula and Ikoyi on Lagos Island.
  • Emergent markets key for formwork sector growth
    May 21, 2014
    Central and south-east Europe are hotbeds for new highway infrastructure projects utilising cutting-edge formwork solutions, while a number of leading formwork manufacturers are also looking at emergent markets for growth. Guy Woodford reports Travelling between Hungary’s capital Budapest and Southern Dalmatia now takes less time thanks to the Pan-European Corridor Vc – European route 73. Numerous tunnels and bridges are erected along the 397km stretch of the European route 73 through Bosnia owing to the
  • Lochkov bridge construction time 'cut'
    July 17, 2012
    As part of the R1 southern orbital motorway around the Czech capital, Prague, a joint venture is building a five-span, 461m long and approximately 65m high viaduct near the village of Lochkov, as a girder bridge construction. For the two steeply inclined twin piers, Doka has supplied an automatic climbing formwork solution that obviates the need for shoring and that will "cut more than 100 days from the construction period." Cast-in-place concrete construction of bridge piers with such a steep inclination
  • Major Central American infrastructure projects
    February 23, 2012
    Mexico and Central America are home to some of the world's most spectacular infrastructure projects as Patrick Smith reports