Climbing in Corpus Christi

The challenge for Doka on the new Harbor Bridge in Texas was to use the same formwork for each pylon despite each pylon’s different geometry.
September 17, 2020 Read time: 2 mins
Doka used its hydraulic climbing formworks SKE50 and SKE100 plus its large-area formwork Top 50

The new US 181 Harbor Bridge is being constructed to replace an ageing bridge across the Corpus Christi Ship Channel off the Gulf of Mexico. The replacement bridge, with nearly a 63m clearance, will also allow the passage of larger ships and possibly cruise ships into the docks. The current Harbor Bridge was opened in 1956 to replace a drawbridge and now handles 26,000 vehicles per day. When complete, the new Harbor Bridge will be the tallest point in southern Texas and the longest cable-stayed concrete segmental bridge in the US.

The upper and lower pylons were different shapes requiring two designs. The primary pylon structures have a geometry that narrows and angles at the same time. A reusable system was needed that would have minimal changes between pours.

Doka used large-area formwork Top 50 as well as hydraulic climbing formwork SKE50 and SKE100 platforms. The system was designed with telescopic platforms that adjust to the changing pylon shape. Doka says there were almost 520m² of formwork for one pylon.

Doka helped the contractor – a Flatiron and Dragados joint venture - remain on schedule because there was minimal rebuild between pours. Doka also saved crane time due to the hydraulic lifting systems employed.

The contract won by Flatiron and Dragados includes $854.6 million for design and construction of the bridge and another $128.2 million for the 25-year maintenance and operation of the bridge.

For more information on companies in this article

Related Content

  • Dragados among six in the running for fourth Panama bridge deal
    August 23, 2016
    All six consortia that submitted documents in May to design and build a fourth bridge over the Panama Canal have pre-qualified, according to media reports. The companies officially vying for the estimated US$1 billion contract are: • Dragados • Consorcio CCB: Constructora Norberto Odebrecht, Odebrecht Engenharia e Construcao International • Consorcio Hyundai, Sacyr JV • Consorcio Astaldi – Daelim • Consorcio Panamá Cuarto Puente: China Communications Contruction Company, China Harbour Engi
  • Cranes help construct major bridge project in CHina
    September 8, 2014
    A number of tower cranes have helped complete the Chishi Grand Bridge project in China Six Potain tower cranes were used to build two 280m tall bridge pylons, high in the clouds above the mountains of southern China. The cranes spent 30 months building the pylons at the Chishi Grand Bridge, which will span 1.47km and carry its road deck 180m above the ground. The bridge will open at the end of 2014.
  • Cranes help construct major bridge project in China
    September 8, 2014
    A number of tower cranes have helped complete the Chishi Grand Bridge project in China. Six Potain tower cranes were used to build two 280m tall bridge pylons, high in the clouds above the mountains of southern China. The cranes spent 30 months building the pylons at the Chishi Grand Bridge, which will span 1.47km and carry its road deck 180m above the ground. The bridge will open at the end of 2014.
  • RMD formwork for Qatar’s tallest bridge on Doha East Corridor
    July 6, 2016
    RMD Kwikform will be supplying tens of thousands of tonnes of its formwork and shoring for construction of Qatar’s tallest bridge on the Doha East Corridor project As well as the bridge, the Corridor contract comprises four interchanges at a total cost of US$612.5 million. Ashghal, Qatar's Public Works Authority, awarded the Corridor project to China Harbour Engineering Design and Construction. Built as a five-lane 11km bypass in Doha, the capital of Qatar, the project will also cater for a rail line