Climbing in Corpus Christi

The challenge for Doka on the new Harbor Bridge in Texas was to use the same formwork for each pylon despite each pylon’s different geometry.
September 17, 2020 Read time: 2 mins
Doka used its hydraulic climbing formworks SKE50 and SKE100 plus its large-area formwork Top 50

The new US 181 Harbor Bridge is being constructed to replace an ageing bridge across the Corpus Christi Ship Channel off the Gulf of Mexico. The replacement bridge, with nearly a 63m clearance, will also allow the passage of larger ships and possibly cruise ships into the docks. The current Harbor Bridge was opened in 1956 to replace a drawbridge and now handles 26,000 vehicles per day. When complete, the new Harbor Bridge will be the tallest point in southern Texas and the longest cable-stayed concrete segmental bridge in the US.

The upper and lower pylons were different shapes requiring two designs. The primary pylon structures have a geometry that narrows and angles at the same time. A reusable system was needed that would have minimal changes between pours.

Doka used large-area formwork Top 50 as well as hydraulic climbing formwork SKE50 and SKE100 platforms. The system was designed with telescopic platforms that adjust to the changing pylon shape. Doka says there were almost 520m² of formwork for one pylon.

Doka helped the contractor – a Flatiron and Dragados joint venture - remain on schedule because there was minimal rebuild between pours. Doka also saved crane time due to the hydraulic lifting systems employed.

The contract won by Flatiron and Dragados includes $854.6 million for design and construction of the bridge and another $128.2 million for the 25-year maintenance and operation of the bridge.

For more information on companies in this article

Related Content

  • The bridge to reduced traffic
    February 28, 2012
    In Zaporozhye, the industrial metropolis in Ukraine's south-east, a multi-lane cable stayed bridge is being built alongside an older viaduct. On completion, this large-scale infrastructure project will massively reduce the traffic burden on the existing bridge and significantly improve the daily traffic situation at this major river crossing.
  • PERI's tall order in Mexico
    February 14, 2012
    The Baluarte Bridge (Puente Baluarte), part of a major highway project, ranks among the most outstanding infrastructure projects ever constructed in Mexico.
  • Towers of power: California’s Gerald Desmond Bridge Replacement
    May 8, 2019
    Challenging ground conditions meant a design rethink - and some engineering firsts - for California’s Gerald Desmond Bridge Replacement Project* The Port of Long Beach on Terminal Island south of Los Angeles is the second-busiest container port in the US. It handles around 15% of all imported goods, much of it with Asia. As the Port of Long Beach was growing in importance over the past half century, the 51-year-old Gerald Desmond Bridge has faithfully been delivering thousands of daily commuters to wo
  • Bridging the gap in African infrastructure
    December 20, 2013
    Leading formwork manufacturers have secured some impressive contracts in Africa, as the continent’s transport infrastructure continues to improve at a rapid pace. Meanwhile, other bridgework equipment companies are also seeing their products in demand in Africa, as well as North America and Australia.