Atlas Copco attachments make short work of the A8 Blaubeurer Weg Bridge

A reinforced concrete bridge over the Autobahn 8 between Merklingen and Nellingen in southern Germany was demolished overnight due in no small part to the efficient, reliable performance of Atlas Copco hydraulic attachments. In addition to demolition grippers, breakers and pulverisers, the demolition team used the HM 2000 hydraulic magnet to demolish structures and sort demolition waste. There is now nothing to stop the widening of the A8 to six lanes or construction of the parallel high-speed Wendlingen
March 21, 2016 Read time: 3 mins
A reinforced concrete bridge over the Autobahn 8 between Merklingen and Nellingen in southern Germany was demolished overnight due in no small part to the efficient, reliable performance of 161 Atlas Copco hydraulic attachments.

In addition to demolition grippers, breakers and pulverisers, the demolition team used the HM 2000 hydraulic magnet to demolish structures and sort demolition waste. There is now nothing to stop the widening of the A8 to six lanes or construction of the parallel high-speed Wendlingen-to-Ulm railway link.

"A logistical masterpiece," is how Jörg Hamann, spokesman for Deutsche Bahn Projekt Stuttgart–Ulm, described the work. Demolition, including all ancillary tasks, was scheduled to be completed within just 14 hours and contractor Weilheim finished the task well within the given time.

They used eight 178 caterpillar excavators with an operative weight of up to 50tonnes to remove the 1,500-tonne "Blaubeurer Weg" reinforced concrete bridge measuring 64m long and 6m wide. Several heavy-duty Atlas Copco grippers, breakers and concrete pulverisers weighing up to 4tonnes were used as attachments.

"Such structures would have been dynamited in the past," said Joachim Schmid, the demolition company’s chief executive. "Coming back to finish the task the next day was not an option here."

Tasks were completed in quick succession. As soon as roads were blocked off, workers disassembled the crash barriers and central reservations and then laid down non-woven fabric and gravel to protect the road surface. Next, the bridge railings were removed followed by the solid concrete sections and the entire superstructure.
Technical procedures for bridge demolition can be broadly similar every time, but each project has its own special characteristics, “a unique structure," said Schmid.

This particular overpass spanning the A8 did not feature a central support. As a result, excavators could not operate from above, the usual approach, but only from down below.

It was, therefore, all the more important that attachments could be applied exactly where they were needed using precisely the right amount of force.

It was not only the time-tested grippers and breakers which helped to dismantle the bridge successfully; an HM 2000 Hydro Magnet also gave an impressive performance. As a rigid magnet for carrier vehicles between 14-45tonnes, it is particularly suitable for separating scrap metal from other demolition waste. It ensures greater profit thanks to optimum use of scrap steel and also provides fast, highly effective sorting and efficient recycling. What's more, cleared construction sites mean significantly less damage is sustained by machines and equipment.

Now that the bridge is completely removed, the Deutsche Bahn project company has started construction of the A8 overpass with an overall length of around 87m and a height of up to 6.4m. Costing around €600,000, the replacement structure should be finished by January 2017.

For more information on companies in this article

Related Content

  • Using breakers to demolish redundant overpass
    December 11, 2015
    A demolition job in California was carried out successfully using a hydraulic breaker fitted to an excavator. An overpass on Highway 91 in Southern California had to be removed, with the contractor opting to use a hydraulic breaker for the job. The work was carried out within the 22-hour possession period set by the local authorities, allowing the route to reopen to traffic on time and minimising transport delays. The work was carried out safely and precisely, due to the use of suitable equipment. The re
  • CECE sets up new group for hydraulic attachments
    February 25, 2014
    The European Construction Equipment Committee, CECE, has broadened its portfolio with the formation of a new body. It has recently established a new product group for hydraulic attachment tools. The body serves as a communication and information platform for companies operating in this business segment, including companies such as Arden Equipment, Atlas Copco, Caterpillar, FRD, Indeco, Montabert, NPK, Okada, Sandvik, Simex, Socomec, Soosan, Tabe, Toku and VTN. The product group is chaired by Torsten Ahr,
  • Atlas Copco claims improved bucket crushing
    October 27, 2016
    High throughput and long wear life are claimed by Atlas Copco for its latest bucket crusher attachments. The new BC 2500 and BC 3700 are said to offer higher output and better reliability than previous models. The new units can process up to 80% more material than earlier designs due to new hydraulic drives. The BC 2500 is suited to carriers weighing from 24-33tonnes while the larger BC 3700 can be fitted to excavators weighing from 30-42tonnes. The firm claims that the new bucket crushers allow cont
  • Indeco cuts up New York City’s old Kosciuszko Bridge
    November 23, 2017
    An Indeco ISS 45/90 is proving essential for demolishing the old Kosciuszko Bridge in New York City. New York City’s old 1.9km Kosciuszko Bridge, which crosses Newtown Creek connecting Green Point, Brooklyn with Maspeth, Queens, has been out of service since April. By the end of the year, the polygonal Warren through-truss structure will be no more. To replace the old bridge, in 2009, the New York State Department of Transportation planned the construction of two cable-stayed replacement bridges.