Atlas Copco attachments make short work of the A8 Blaubeurer Weg Bridge

A reinforced concrete bridge over the Autobahn 8 between Merklingen and Nellingen in southern Germany was demolished overnight due in no small part to the efficient, reliable performance of Atlas Copco hydraulic attachments. In addition to demolition grippers, breakers and pulverisers, the demolition team used the HM 2000 hydraulic magnet to demolish structures and sort demolition waste. There is now nothing to stop the widening of the A8 to six lanes or construction of the parallel high-speed Wendlingen
March 21, 2016 Read time: 3 mins
A reinforced concrete bridge over the Autobahn 8 between Merklingen and Nellingen in southern Germany was demolished overnight due in no small part to the efficient, reliable performance of 161 Atlas Copco hydraulic attachments.

In addition to demolition grippers, breakers and pulverisers, the demolition team used the HM 2000 hydraulic magnet to demolish structures and sort demolition waste. There is now nothing to stop the widening of the A8 to six lanes or construction of the parallel high-speed Wendlingen-to-Ulm railway link.

"A logistical masterpiece," is how Jörg Hamann, spokesman for Deutsche Bahn Projekt Stuttgart–Ulm, described the work. Demolition, including all ancillary tasks, was scheduled to be completed within just 14 hours and contractor Weilheim finished the task well within the given time.

They used eight 178 caterpillar excavators with an operative weight of up to 50tonnes to remove the 1,500-tonne "Blaubeurer Weg" reinforced concrete bridge measuring 64m long and 6m wide. Several heavy-duty Atlas Copco grippers, breakers and concrete pulverisers weighing up to 4tonnes were used as attachments.

"Such structures would have been dynamited in the past," said Joachim Schmid, the demolition company’s chief executive. "Coming back to finish the task the next day was not an option here."

Tasks were completed in quick succession. As soon as roads were blocked off, workers disassembled the crash barriers and central reservations and then laid down non-woven fabric and gravel to protect the road surface. Next, the bridge railings were removed followed by the solid concrete sections and the entire superstructure.
Technical procedures for bridge demolition can be broadly similar every time, but each project has its own special characteristics, “a unique structure," said Schmid.

This particular overpass spanning the A8 did not feature a central support. As a result, excavators could not operate from above, the usual approach, but only from down below.

It was, therefore, all the more important that attachments could be applied exactly where they were needed using precisely the right amount of force.

It was not only the time-tested grippers and breakers which helped to dismantle the bridge successfully; an HM 2000 Hydro Magnet also gave an impressive performance. As a rigid magnet for carrier vehicles between 14-45tonnes, it is particularly suitable for separating scrap metal from other demolition waste. It ensures greater profit thanks to optimum use of scrap steel and also provides fast, highly effective sorting and efficient recycling. What's more, cleared construction sites mean significantly less damage is sustained by machines and equipment.

Now that the bridge is completely removed, the Deutsche Bahn project company has started construction of the A8 overpass with an overall length of around 87m and a height of up to 6.4m. Costing around €600,000, the replacement structure should be finished by January 2017.

For more information on companies in this article

Related Content

  • Controlled demolition development
    January 25, 2017
    The development of reliable hydraulic attachments has brought a revolution in demolition technology. The hydraulic breaker, pioneered by the Krupp and Montabert brands, has firmly taken hold with a huge range of manufacturers now offering machines. Hydraulic attachment specialists such as Atlas Copco, Indeco and Sandvik (with its Rammer brand) now offer a range of tools that can deliver high efficiency and safety in demolition work. Meanwhile, developments with smaller tools offer productive methods for rep
  • High speed bridge demolition minimises disruption
    February 16, 2012
    A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.
  • High speed bridge demolition minimises disruption
    April 13, 2012
    A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.
  • Atlas Copco for Brazil bridge demolition
    July 2, 2013
    Brazilian demolition specialist Comprex was chosen to demolish a bridge connecting districts in the city of Vitória in the state of Espirito Santo. For environmental reasons, debris was not permitted to fall into the waterway under the bridge, and special arrangements had to be made for the removal of the demolition waste. Comprex chose Atlas Copco hydraulic breakers and CombiCutters for the jobsite where three new bridges have been built over the old bridge, which was no longer able to support the increasi