Zalazone test track gears up

Work on the US$159 million Zalazone project started in 2017 and is on schedule.
By David Arminas June 5, 2020 Read time: 2 mins
Zalazone’s braking platform is for ABS, ATC and ESP tests (photo Zalazone/palyamodulok_03a)

The second phase of Hungary’s 265-hectare autonomous vehicle Zalazone test track is nearing completion, according to the minister of innovation.

Laszlo Palkovics said the US$159 million project which started in 2017 is on schedule and progressing in three phases. The track is near Zalaegerszeg, around 180km southwest of Budapest

Phase one involved setting up basic elements such a braking platform, a vehicle handling course and a typical country road layout. The braking platform is designed to carry out ABS, ATC and ESP tests along eight types of surfaces and watering systems and also allows for high-speed platooning tests.

Phase one also saw the start of the Smart City area, a city-like area to provide realistic traffic circumstances in a closed area that contains more environmental, traffic, traffic engineering and vehicle dynamic elements.

The second phase, now nearing completion, includes a high-speed oval, bad roads and slopes and additional aspects of the Smart City.

Phase three will be development from 2022 onwards, according to the organisation’s website. It will add more facilities to the Smart City Zone such as more types of lanes, surfaces and road geometry. Different type of building and facades will be placed next to the street grid of Smart City Zone.

Budapest University of Technology, University of Pannonia and Széchenyi Istvány University do much of their vehicular and transportation research at Zalazone.

Related Content

  • Developments in concrete road construction
    February 7, 2012
    Innovative developments are pushing forward concrete road construction techniques. The concrete road sector looks to benefit from some key innovations and developments now coming to market or being employed in different territories. Irregular weather and environmental conditions can alter the rate at which concrete cures, with a risk of plastic shrinkage cracks that can compromise the integrity of a pavement. Contractors cannot control the environmental conditions of a paving project and when weather patter
  • ERIC 2016: What shape the ‘Smart Road’?
    February 7, 2017
    Optimism about the future of highways worldwide abounded at the inaugural European Road Infrastructure Conference (ERIC) in Leeds, UK Around 500 delegates passed through the varied sessions during the three-day event at the Royal Armouries Museum in the northern English city of Leeds. They came away with many visions of what a motorway and road could look like. But what speakers at the event - co-organised by the Brussels-based European Union Road Federation (ERF) and the UK’s Road Safety Markings Ass
  • COWI wins Massey Tunnel design contract
    February 18, 2022
    COWI will develop an eight-lane immersed tunnel for the George Massey Crossing Project near Vancouver, Canada.
  • Lower traffic emissions in London
    May 20, 2019
    London’s ultra-low emission zone (ULEZ) system is already proving successful. In the first month since the scheme was introduced, the number of non-compliant vehicles entering the charging zone has been reduced by 9,400/day, a drop of 26%. According to the latest research, 74% of vehicles entering the ULEZ have been in compliance with the emission requirements.