VIDEO: Gap closed for Gordie Howe Bridge

A 26m gap in the deck was recently closed on the bridge that will connect Detroit in the US state of Michigan and Windsor in the Canadian province of Ontario.
By David Arminas July 26, 2024 Read time: 3 mins
Workers will now stress stay cables (image courtesy Windsor-Detroit Bridge Authority - WDBA

Canadian and American workers on the Gordie Howe International Bridge recently celebrated the final steps taken to close the deck gap on the US$4.7 billion structure.

The 26m gap was closed this month on the bridge that will connect Detroit in the US state of Michigan and Windsor in the Canadian province of Ontario.

The 853m main bridge deck between the two towers makes it the longest main span of any cable-stayed bridge in North America and the tenth longest in the world. Clearance above the river is 42m. It will also be the longest composite steel and concrete bridge deck for any cable-stayed bridge in the world, according to the Windsor-Detroit Bridge Authority (WDBA), a not-for-profit Canadian Crown corporation created to deliver the project through a public-private partnership.

WDBA is responsible for overseeing and managing the construction and operation of the new crossing. Meanwhile, Bridging North America, BNA, is the main joint venture contractor - Fluor, ACS Infrastructure Canada and Aecon Group - for the design, build, finance, operation and maintenance of the project.

Workers will now stress stay cables and install electrical, fire suppression and drainage systems, barriers, signage, lighting, deck paving and pavement markings and complete the multi-use path.

Early work for the bridge started in summer 2018 and it was originally set to open in November 2024. But disruptions due to the COVID-19 pandemic pushed back the date and increased costs from the original $4.3 billion.

Bridging North America said that the four-week, multi-step, precision process to close the gap included the placement and removal of temporary bents and the installation of the final steel girders, beams, panels and precast concrete.

“The team has worked incredibly hard since 2018 to achieve this important project milestone,” said Shawn West, president of Fluor’s infrastructure business. “The connection of this iconic bridge serves as a testament to our dedication and perseverance to build safe and reliable infrastructure. This bridge will soon serve as a major gateway between Canada and the United States.”

While the main focus of construction has been on the bridge deck, progress is also being made on the Ports of Entry in Canada and the US, as well as the connection to I-75. When completed in autumn next year, the bridge will include six lanes of traffic, two ports of entry, a multi-use path, a new interchange at I-75 with four new road bridges, five pedestrian bridges and four interchange ramps connecting I-75 to the U.S. Port of Entry. Fluor and ACS will operate and maintain the facility for 30 years for the WDBA.

The Canadian government will receive all toll revenues, the project being totally Canadian with no US funding.

For more information on companies in this article

Related Content

  • Construction of the Gordie Howe Bridge could start in mid-2018
    May 12, 2017
    Construction of the US$2.1 billion Gordie Howe International Bridge is expected to start in late 2018, according to the authority in charge of the project. Preliminary early works on bridge – the second to span the Detroit River ? between Detroit, Michigan in the US and Windsor, in the Canadian province of Ontario have started. A main contractor is likely to be appointed by mid next year. The first phase of early works has focused on fill placement, construction of a perimeter access road and minor utility
  • Construction of the Gordie Howe Bridge could start in mid-2018
    May 12, 2017
    Construction of the US$2.1 billion Gordie Howe International Bridge is expected to start in late 2018, according to the authority in charge of the project. Preliminary early works on bridge – the second to span the Detroit River ? between Detroit, Michigan in the US and Windsor, in the Canadian province of Ontario have started. A main contractor is likely to be appointed by mid next year. The first phase of early works has focused on fill placement, construction of a perimeter access road and minor utility
  • US land sale completed for US-Canada Gordie Howe Bridge
    June 27, 2017
    Detroit has reached an agreement with the state to sell land, assets and some streets as part of a second bridge between Windsor and Detroit.
  • Canada, US officials soon to settle planned Detroit bridge issue
    February 5, 2015
    An end to a thorny issue is close at hand concerning who will fund construction of a border customs plaza on the US side of a planned bridge linking Canada and the United States. US President Barack Obama’s US$4-trillion budget did not set aside any money for the plaza for a second consecutive year, further irritating Canadian officials who are overseeing construction of the bridge. It appears that the Canadian government might end up footing the entire bill, according to a report in Toronto’s Globe a