Unexpected problems delay Swiss highway project

A highway project looks set to face extended delays in its construction due to the discovery of contaminated land. A two year highway project planned in the canton Valais will now take considerably longer to complete due to the unexpected discovery of mercury contamination on the site. The contamination is historic and appears to be the result of disposal carried out by a local chemicals firm in the 1930s, when there were few controls over what could be dumped. The company had tipped its chemical waste into
November 28, 2012 Read time: 2 mins
A highway project looks set to face extended delays in its construction due to the discovery of contaminated land. A two year highway project planned in the canton Valais will now take considerably longer to complete due to the unexpected discovery of mercury contamination on the site. The contamination is historic and appears to be the result of disposal carried out by a local chemicals firm in the 1930s, when there were few controls over what could be dumped. The company had tipped its chemical waste into a canal but the scale of the contamination has yet to be fully assessed. The project requires some 240,000m3 of earthmoving work and at this early stage, it looks as if some 20,000m3 will have to be treated. The chemicals firm is still in business and will pay for the extra decontamination work necessary. However, the issue does highlight the problem of historic contamination dating from when environmental controls were less thorough than at present. With the need to re-use many former industrial sites for infrastructure work in developed nations, this type of problem is likely to resurface on a regular basis.

Related Content

  • ECT's sustainability in action
    February 7, 2012
    French company ECT (Enviro Conseil Travaux) has opted to take advantage of the Caterpillar Certified Power Train (CPT) rebuild service for two of its Cat 740 Ejector articulated trucks. These are the first rebuilds worldwide for articulated trucks, and both were carried out by the French Cat dealer Bergerat Monnoyeur. What you get with CPT: Restores power train to like-new performance, Covers radiator, engine, transmission, torque converter, final drive and axle, Approximately 200 tests and inspections of p
  • UK government calls satnav summit to tackle mapping problems
    March 1, 2012
    UK local transport minister, Norman Baker has announced he will host the governments first 'satnav summit' early in March to thrash out solutions to end the misery caused when lorry and car drivers follow out of date directions from their satnavs.
  • CET opens new laboratory to service UK’s infrastructure projects
    October 23, 2017
    With over £300 billion of investment in infrastructure planned over the next four years in the UK, materials testing firm CET is gearing up to service a lot more projects – Kristina Smith visited the newest laboratory near Heathrow to find out more. The CET Group has ambitious plans. Over the next four years it wants to double the size of its business, which in the last year turned over £27 million. “There’s a lot of positivity out there,” said Gary Corrigan, managing director of the group’s infrastructu
  • Reduced pollution with locally sourced materials
    February 24, 2012
    Robert Petts provides a practical example of gTKP at work. There is a substantial requirement for a range of sealers and binders in the global road infrastructure sector. The principal need is for the construction and maintenance of road surfaces and pavements. Globally, more than 100 million tonnes of bitumen are produced each year, mostly for use in the road sector.