Tender call for US$940mn phase I of Chile’s Américo Vespucio Oriente highway

A tender call for the first, US$940 million stretch of the Américo Vespucio Oriente underground expressway (AVO) in Chile’s capital Santiago Chile's has been issued by the public works ministry (MOP). The prized 40-year concession entails building and operating a 9.3km underground expressway running from El Salto avenue to Príncipe de Gales avenue. The tunnel will stretch over two different levels, each one hosting a one-way, three-lane expressway. Road capacity along the route will increase to 8,000 vehicl
August 1, 2013 Read time: 2 mins
A tender call for the first, US$940 million stretch of the Américo Vespucio Oriente underground expressway (AVO) in Chile’s capital Santiago Chile's has been issued by the public works ministry (MOP).

The prized 40-year concession entails building and operating a 9.3km underground expressway running from El Salto avenue to Príncipe de Gales avenue. The tunnel will stretch over two different levels, each one hosting a one-way, three-lane expressway.

Road capacity along the route will increase to 8,000 vehicles per hour from a current 3,000 vehicles per hour, in a push to mitigate the city increasing traffic jams.

The AVO project was originally conceived of to be the missing link in a beltway that runs around Santiago. As such, it was originally earmarked to span underground north to south for 13km, joining El Salto with the Rotonda Grecia.

However, opposition from inhabitants of the La Reina and Peñalolén districts to the last 4km-stretch of the tunnel pushed the government, which is leaving office in March 2014, to split the project and call a tender only for the first 9.3km stretch.

The responsibility for the AVO's final stretch will pass on to the new elected president. The current government led by Sebastian Piñera will leave office four months after the presidential election takes place in November 2013.

Parties interested in bidding for the first stretch have until November 22 to submit their offers.

Related Content

  • Key Chile road project is delayed starting
    September 26, 2017
    Construction work on Chile’s Americo Vespucio Oriente 1 (AVO 1) highway is starting somewhat later than was originally planned. Originally construction of the new highway was to have commenced in September 2016, but this was then held back first to July 2017 and finally to October 2017.
  • Major plans for Chilean infrastructure development
    March 14, 2014
    A major plan for infrastructure is being put forward for Chile. Chile's Construction chamber (CChC) has presented a plan for some US$40 billion in infrastructure improvements to the new Chilean Government. The CChC has highlighted the concession model as being the most effective tool for encouraging private investment in infrastructure. The CChC suggests that Chile has a critical need for infrastructure development, but a serious shortfall of public funds according to a report by Business News Americas. Roa
  • Chile’s Chacao bridge project generates just one consortium technical bid
    November 8, 2013
    Only one consortium has submitted a technical bid in the tender for a project to build the Chacao bridge in Chile. The bridge will link Chiloe island with Chile’s mainland Los Lagos region. The Chilean government has earmarked a maximum project budget of US$740 million. The consortium that has submitted the technical bid, which would see the construction of a four-lane bridge, is made up of Hyundai of South Korea, Systra of France, Brazilian company OAS and Aas-Jakobsen of Norway. The consortium has
  • Colombian concession contracts cause concern
    June 13, 2014
    A report from insurance firm AIG warns that up to half of Colombia's 4G highway concessions could face financial hurdles due to over-estimated predictions of traffic flows. Colombia is at present putting out to tender its fourth generation (4G) concessions, which involve some US$25 billion in investment, reports Business News America. This investment is impressive and is Latin America's biggest move to expand and improve road infrastructure. But while many companies have shown interest and were prequalified